Problem 5A-8 High-Low Method; Predicting Cost [LO5-10]
Nova Company’s total overhead cost at various levels of activity are presented below:
Month | Machine- Hours |
Total Overhead Cost |
|||
April | 46,000 | $ | 179,200 | ||
May | 36,000 | $ | 156,700 | ||
June | 56,000 | $ | 201,700 | ||
July | 66,000 | $ | 224,200 | ||
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is:
Utilities (variable) | $ | 43,200 |
Supervisory salaries (fixed) | 61,000 | |
Maintenance (mixed) | 52,500 | |
Total overhead cost | $ | 156,700 |
Nova Company’s management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $224,200 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $224,200 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the company’s total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 41,000 machine-hours?
1 | Variable Utilities cost per Machine hour($43,200/36,000 hrs) | $ 1.20 | |
Total Overhead Cost at 66,000 machine hours | $ 2,24,200 | ||
Less:Utilities Costs(66,000*$1.20) | $ 79,200 | ||
Less:Supervisory Salaries Costs | $ 61,000 | ||
Maintaiance Costs | $ 84,000 | ||
2 | Maintainance Costs | ||
Machine Hours | Maintainance Costs | ||
High level of activity | 66,000 | $84,000 | |
Low level of activity | 36,000 | $52,500 | |
Change | 30,000 | $31,500 | |
Variable cost per MHrs =$31,500 / 30,000 =$1.05 per machine hrs | |||
Fixed cost element =$84,000 - (66,000*$1.05) | |||
Y =$14,700 + $1.05X | |||
3 | Total Overhead Costs | ||
Machine Hours | Overhead Costs | ||
High level of activity | 66,000 | $2,24,200 | |
Low level of activity | 36,000 | $1,56,700 | |
Change | 30,000 | $67,500 | |
Variable cost per MHrs =$67,500 / 30,000 =$2.25 per machine hrs | |||
Fixed cost element =$224,200 - (66,000*$2.25) | |||
Y =$75,700 + $2.25X | |||
4 | Cost to be incurred at 41,000 machine hrs =$75,700 + $2.25*41,000 =$167,950 | ||
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...
PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...
Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...
Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 180,540 May 36,000 $ 156,640 June 56,000 $ 204,440 July 66,000 $ 228,340 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 58,000 Maintenance (mixed) 55,440 Total overhead cost $ 156,640 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 180,200 May 37,000 $ 156,200 June 57,000 $ 204,200 July 67,000 $ 228,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 55,000 Maintenance (mixed) 53,100 Total overhead cost $ 156,200 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 178,520 May 42,000 $ 155,920 June 62,000 $ 201,120 July 72,000 $ 223,720 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 50,400 Supervisory salaries (fixed) 42,000 Maintenance (mixed) 63,520 Total overhead cost $ 155,920 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 193,480 May 38,000 $ 169,880 June 58,000 $ 217,080 July 68,000 $ 240,680 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 45,600 Supervisory salaries (fixed) 67,000 Maintenance (mixed) 57,280 Total overhead cost $ 169,880 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 182,640 May 42,000 $ 158,940 June 62,000 $ 206,340 July 72,000 $ 230,040 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 54,600 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 60,340 Total overhead cost $ 158,940 Nova Company’s...