Question

Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

Problem 5A-8 High-Low Method; Predicting Cost [LO5-10]

Nova Company’s total overhead cost at various levels of activity are presented below:

Month Machine-
Hours
Total
Overhead
Cost
April 46,000 $ 179,200
May 36,000 $ 156,700
June 56,000 $ 201,700
July 66,000 $ 224,200

Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is:

Utilities (variable) $ 43,200
Supervisory salaries (fixed) 61,000
Maintenance (mixed) 52,500
Total overhead cost $ 156,700

Nova Company’s management wants to break down the maintenance cost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $224,200 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $224,200 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)

2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.

3. Express the company’s total overhead cost in the form Y = a + bX.

4. What total overhead cost would you expect to be incurred at an activity level of 41,000 machine-hours?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Variable Utilities cost per Machine hour($43,200/36,000 hrs) $                                  1.20
Total Overhead Cost at 66,000 machine hours $                           2,24,200
Less:Utilities Costs(66,000*$1.20) $                              79,200
Less:Supervisory Salaries Costs $                              61,000
Maintaiance Costs $                              84,000
2 Maintainance Costs
Machine Hours Maintainance Costs
High level of activity                                  66,000 $84,000
Low level of activity                                  36,000 $52,500
Change                                  30,000 $31,500
Variable cost per MHrs =$31,500 / 30,000 =$1.05 per machine hrs
Fixed cost element =$84,000 - (66,000*$1.05)
Y =$14,700 + $1.05X
3 Total Overhead Costs
Machine Hours Overhead Costs
High level of activity                                  66,000 $2,24,200
Low level of activity                                  36,000 $1,56,700
Change                                  30,000 $67,500
Variable cost per MHrs =$67,500 / 30,000 =$2.25 per machine hrs
Fixed cost element =$224,200 - (66,000*$2.25)
Y =$75,700 + $2.25X
4 Cost to be incurred at 41,000 machine hrs =$75,700 + $2.25*41,000 =$167,950
Add a comment
Know the answer?
Add Answer to:
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...

  • PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of...

    PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...

  • Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...

  • Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 180,540 May 36,000 $ 156,640 June 56,000 $ 204,440 July 66,000 $ 228,340 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 58,000 Maintenance (mixed) 55,440 Total overhead cost $ 156,640 Nova Company’s...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 180,200 May 37,000 $ 156,200 June 57,000 $ 204,200 July 67,000 $ 228,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 55,000 Maintenance (mixed) 53,100 Total overhead cost $ 156,200 Nova Company’s...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 178,520 May 42,000 $ 155,920 June 62,000 $ 201,120 July 72,000 $ 223,720 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 50,400 Supervisory salaries (fixed) 42,000 Maintenance (mixed) 63,520 Total overhead cost $ 155,920 Nova Company’s...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 193,480 May 38,000 $ 169,880 June 58,000 $ 217,080 July 68,000 $ 240,680 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 45,600 Supervisory salaries (fixed) 67,000 Maintenance (mixed) 57,280 Total overhead cost $ 169,880 Nova Company’s...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 182,640 May 42,000 $ 158,940 June 62,000 $ 206,340 July 72,000 $ 230,040 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 54,600 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 60,340 Total overhead cost $ 158,940 Nova Company’s...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT