1.Maintenance cost at the 90,000 machine-hour level of activity can be calculated as follows:
Level of Activity 60,000 90,000
MH MH
Total factory overhead cost $174,000 $246,000
Less: Utilities cost @ $0.8 per MH $48,000 $72,000
Supervisory salaries $21,000 $21,000
__________ _________
Maintenance cost $105,000 $153,000
Utilities Cost per machine hour = $48,000 ÷ 60,000 MHs = $0.8 per MH
Maintenance cost for July is $153,000.
2.High-low analysis of maintenance cost:
Machine Maintenance
Hours Cost
High activity level 90,000 $153,000
Low activity level 60,000 $105,000
Change 30,000 $48,000
Variable cost per unit of activity:
Change in cost/Change in Hours
= $48,000/30,000MH = $1.6 per MH
Total fixed cost:
Total maintenance cost at the low activity level $105,000
Less: Variable cost element
(60,000 MHs × $1.6 per MH) ($96,000)
Fixed cost element $9,000
Thus, the cost formula is $9,000 per month plus $1.6 per machine-hour or
Y = $19,000 + $1.6X
3. Variable Rate per Fixed Cost
Machine-Hour
Maintenance cost $1.6 $9,000
Utilities cost $0.8
Supervisory salaries cost $21,000
Totals $2.4 $30,00
Thus, the cost formula is: Y = $30,00 + $2.4X.
4.Total overhead cost at an activity level of 75,000 machine-hours:
Fixed cost $30,000
Variable costs: $2.4 per MH*45,000 MHs $180,000
_________
Total overhead costs $210,000
PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 179,200 May 36,000 $ 156,700 June 56,000 $ 201,700 July 66,000 $ 224,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 61,000 Maintenance (mixed) 52,500...
Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...
PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels of activity are presented below: Total Overhead Cost Month Machine Hours April. ..... May .......... June ........ July................... 70,000 60,000 80,000 90,000 $198,000 $174,000 $222,000 $246,000 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000-machine-hour level of activity in May is as follows: Utilities (variable) .......................... $ 48,000 Supervisory salaries (fixed)... 21,000...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 50,000 40,000 60,000 70,000 Total Overhead Cost $ 187,300 $ 161,500 $ 213,100 $ 238,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 56,000 45,000 60,500 $161,500 Nova Company's management...
Nova Company’s total overhead
Nova Company's total overhead cost at various levels of activity are presented below! Month April May June July Total Machine - Overhead Hours Cost 47,000 $187,050 37,000 $159,550 57,000 $214,550 67,000 $242,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 55,500 40,000 64,050 $159,550 Nova Company's...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...