Question

PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Companys total overhead cost at various levels of activity are pre
Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and m
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.Maintenance cost at the 90,000 machine-hour level of activity can be calculated as follows:

Level of Activity 60,000 90,000

MH MH

Total factory overhead cost $174,000 $246,000

Less: Utilities cost @ $0.8 per MH $48,000 $72,000

Supervisory salaries $21,000 $21,000

__________ _________

Maintenance cost $105,000 $153,000

Utilities Cost per machine hour = $48,000 ÷ 60,000 MHs = $0.8 per MH

Maintenance cost for July is $153,000.

2.High-low analysis of maintenance cost:

Machine Maintenance

Hours Cost

High activity level 90,000 $153,000

Low activity level 60,000 $105,000

Change 30,000 $48,000

Variable cost per unit of activity:

Change in cost/Change in Hours

= $48,000/30,000MH = $1.6 per MH

Total fixed cost:

Total maintenance cost at the low activity level $105,000

Less: Variable cost element

(60,000 MHs × $1.6 per MH) ($96,000)

Fixed cost element $9,000

Thus, the cost formula is $9,000 per month plus $1.6 per machine-hour or

Y = $19,000 + $1.6X

3. Variable Rate per Fixed Cost

Machine-Hour

Maintenance cost $1.6 $9,000

Utilities cost $0.8   

Supervisory salaries cost $21,000

Totals $2.4 $30,00

Thus, the cost formula is: Y = $30,00 + $2.4X.

4.Total overhead cost at an activity level of 75,000 machine-hours:

Fixed cost $30,000   

Variable costs: $2.4 per MH*45,000 MHs $180,000

_________

Total overhead costs $210,000

Add a comment
Know the answer?
Add Answer to:
PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...

  • Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...

  • Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 179,200 May 36,000 $ 156,700 June 56,000 $ 201,700 July 66,000 $ 224,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 61,000 Maintenance (mixed) 52,500...

  • Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...

  • PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels...

    PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels of activity are presented below: Total Overhead Cost Month Machine Hours April. ..... May .......... June ........ July................... 70,000 60,000 80,000 90,000 $198,000 $174,000 $222,000 $246,000 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000-machine-hour level of activity in May is as follows: Utilities (variable) .......................... $ 48,000 Supervisory salaries (fixed)... 21,000...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 50,000 40,000 60,000 70,000 Total Overhead Cost $ 187,300 $ 161,500 $ 213,100 $ 238,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 56,000 45,000 60,500 $161,500 Nova Company's management...

  • Nova Company’s total overhead Nova Company's total overhead cost at various levels of activity are presented...

    Nova Company’s total overhead Nova Company's total overhead cost at various levels of activity are presented below! Month April May June July Total Machine - Overhead Hours Cost 47,000 $187,050 37,000 $159,550 57,000 $214,550 67,000 $242,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 55,500 40,000 64,050 $159,550 Nova Company's...

  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT