Problem 5A-8 High-Low Method; Predicting Cost [LO5-10]
Nova Company’s total overhead cost at various levels of activity are presented below:
Month | Machine- Hours |
Total Overhead Cost |
|||
April | 52,000 | $ | 207,440 | ||
May | 42,000 | $ | 181,740 | ||
June | 62,000 | $ | 233,140 | ||
July | 72,000 | $ | 258,840 | ||
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is:
Utilities (variable) | $ | 63,000 |
Supervisory salaries (fixed) | 56,000 | |
Maintenance (mixed) | 62,740 | |
Total overhead cost | $ | 181,740 |
Nova Company’s management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $258,840 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $258,840 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the company’s total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours?
1) | Utilities | (63000/42000)*72000 | 108000 | ||||
Supervisory Salaries | 56,000 | ||||||
Maintenance (balancing figure) | 94,840 | ||||||
Total overhead cost | 258,840 | ||||||
Maintenance cost in july | 94,840 | ||||||
2) | Estimating formula for maintenance cot | ||||||
MH's | cost | ||||||
high | 72,000 | 94,840 | |||||
low | 42,000 | 62,740 | |||||
Difference | 30,000 | 32,100 | |||||
Variable cost per unit = 32100/30000 | |||||||
1.07 | |||||||
Fixed cost = 94840-72000*1.07 | |||||||
17800 | |||||||
Cost formula | |||||||
Y= | 17,800 | + | 1.07 | X | |||
3) | Companys total overhead cost | ||||||
Variable | Fixed | ||||||
Utilities | 1.3 | ||||||
Supervisory salaries | 56,000 | ||||||
Maintenance cost | 1.07 | 17,800 | |||||
total | 2.37 | 73800 | |||||
cost formula | |||||||
Y= | 73,800 | + | 2.37 | X | |||
4) | total overhead cost | ||||||
Y= | 73,800 | + | 2.37 | X | |||
so | |||||||
fixed cost | 73,800 | ||||||
Variable cost (47000*2.37) | 99540 | ||||||
total overhead cost | 173,340 | answer |
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 179,200 May 36,000 $ 156,700 June 56,000 $ 201,700 July 66,000 $ 224,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 61,000 Maintenance (mixed) 52,500...
Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...
PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...
Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 178,520 May 42,000 $ 155,920 June 62,000 $ 201,120 July 72,000 $ 223,720 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 50,400 Supervisory salaries (fixed) 42,000 Maintenance (mixed) 63,520 Total overhead cost $ 155,920 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 182,640 May 42,000 $ 158,940 June 62,000 $ 206,340 July 72,000 $ 230,040 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 54,600 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 60,340 Total overhead cost $ 158,940 Nova Company’s...
Nova Company’s total overhead Nova Company's total overhead cost at various levels of activity are presented below! Month April May June July Total Machine - Overhead Hours Cost 47,000 $187,050 37,000 $159,550 57,000 $214,550 67,000 $242,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 55,500 40,000 64,050 $159,550 Nova Company's...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 180,200 May 37,000 $ 156,200 June 57,000 $ 204,200 July 67,000 $ 228,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 55,000 Maintenance (mixed) 53,100 Total overhead cost $ 156,200 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 193,480 May 38,000 $ 169,880 June 58,000 $ 217,080 July 68,000 $ 240,680 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 45,600 Supervisory salaries (fixed) 67,000 Maintenance (mixed) 57,280 Total overhead cost $ 169,880 Nova Company’s...