utilities exp. Per MH ($) = |
57400/41000 = |
$1.4 per MH |
1)Segregation of Total OH at 71000 MHs= |
OH Costs $ |
|
Utility cost |
71000*1.4 |
99400 |
Supervisory salaries (fixed) |
70000 |
|
Maintenance cost (bal. fig.) |
93830 |
|
total overhead costs |
263230 |
|
2) segregation of maintenance costs into fixed and variable: |
||
Maintenance Costs $ |
||
Maintenance costs at 71000 MHs |
93830 |
|
Maintenance costs at 41000 MHs |
59930 |
|
Difference of MHs = 30000 MHs |
33900 |
|
Variable Maintenance costs |
33900/30000 = |
1.13 per MH |
Fixed Maintenance costs = |
59930-(41000*1.13) = |
13600 |
3) Maintenance costs (X) formula = |
13600 + 1.13 X |
|
4) Total overhead costs at 46000 MHs: |
||
OH Costs $ |
||
Utility costs (variable) |
46000*1.4= |
64400 |
Supervisory salaries (fixed) |
70000= |
70000 |
Maintenance cost (mixed) |
13600 + (46000*1.13)= |
65580 |
total overhead costs= |
199980 |
Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...
PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 179,200 May 36,000 $ 156,700 June 56,000 $ 201,700 July 66,000 $ 224,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 61,000 Maintenance (mixed) 52,500...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Hours 45,000 35,000 55,000 65,000 Month Cost S 185,650 $ 160,350 $ 210,950 $ 236,250 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: $ 45,500 54,000 60,850 $160,350 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost Nova Company's management...
Nova Company’s total overhead Nova Company's total overhead cost at various levels of activity are presented below! Month April May June July Total Machine - Overhead Hours Cost 47,000 $187,050 37,000 $159,550 57,000 $214,550 67,000 $242,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 55,500 40,000 64,050 $159,550 Nova Company's...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Hours Cost 55,000 205,600 45,000179,600 65,000 75,000 ş 231,600 ş 257,600 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $67,500 49,000 63,100 $179,600 Nova Company's management wants to break down the...
Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY June July Machine- Hours 51.000 41.000 61,000 71,000 Total Overhead Cost $ 181,310 $ 158,210 $ 204, 410 $227,510 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,200 51,000 58,010 $158,210 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...