Question

PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Companys total overhead costs at various levels of activi

Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these cost

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part 1

Maintenance cost in July

$153000

Maintenance cost at the 90,000 machine-hour level of activity can be isolated as follows:

Level of Activity

60000 MH

90000 MH

  Total factory overhead cost

$

174,000    

$

246000   

  Deduct:

     Utilities cost @ $0.80 per MH*

48000    

72000   

     Supervisory salaries

21,000    

21,000   

  Maintenance cost

$

105000    

$

153000   

$48000 ÷ 60,000 MHs = $0.80 per MH

Part 2

Y =

$41000

+

$1.60 X

High-low analysis of maintenance cost:

Machine
Hours

Maintenance
Cost

  High activity level

90,000       

$ 153000     

  Low activity level

60,000       

105000     

  Change

30,000       

$ 48000     

  Variable cost per unit of activity:

Change in cost/ change in activity = 48000/30000 = 1.60 per MH

Total fixed cost:

  Total maintenance cost at the low activity level

$

105000   

  Less the variable cost element
      (40,000 MHs × $1.60 per MH)

64000   

  Fixed cost element

$

41000   

Part 3

Y =

$62000

+

$2.40 X

Y = a + bX

a = fixed cost

b = variable cost

Variable Rate per Machine-Hour

Fixed Cost

  Maintenance cost

$ 1.60          

$ 41000     

  Utilities cost

0.80          

  Supervisory salaries cost

21000     

  Totals

$ 2.40          

$ 62000     

Therefore

Y = $62000 + $2.40X

Part 4

Total overhead cost

$242000

Total overhead cost = 62000+(2.40*75000) = $242000

Add a comment
Know the answer?
Add Answer to:
PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of...

    PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...

  • Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...

  • Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...

  • Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May...

    Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May Machine Hours 19,000 39,000 59,000 69.000 Total Overhead Cost $191,860 $164,460 $219, 260 $246,660 July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity in May is as follows: Utilities variable) Supervisory salaries (fixed) Maintenance mixed) 62.400 43.000 59,060 nces Total overhead coat $164.960 The company wants to...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May Machine- Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $210,730 $186,030 $ 235, 430 $260,130 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 50, 700 70,000 65,330 Total overhead cost $ 186,030 The...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $213,580 $189,380 $237,780 $261,980 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 57,200 68,000 64,180 Total overhead cost $ 189,380 The company wants to...

  • 3: Assignment Seved Help Save & Exit Crosshill Company's total overhead costs at various levels of...

    3: Assignment Seved Help Save & Exit Crosshill Company's total overhead costs at various levels of activity are presented below: 5 Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $236,980 $209,280 $264,680 $292,380 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: Book $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 70,400 69,000 69,880...

  • Crosshill Company's total overhead costs at various levels of activity are presented below. chine Total Month...

    Crosshill Company's total overhead costs at various levels of activity are presented below. chine Total Month April May 19.000 39.000 59.000 69.000 $191, 360 164.560 $236.200 July Assume that the overhead cost above consists of utilities, supervisory salaties, and maintenance The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: DELL) Super Scries te $ nes $2.500 43.000 59.06 16. The company wants to break down the maintenance cost into ts variable and feed...

  • Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT