Perit Industries has $135,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Project A Project B $135,000 Cost of equipment required Working capital investment required Annual cash inflowS Salvage value of equipment in six years Life of the project 0 $135,000 25,000 63,000 $ 9,800 6 years 6 years The working capital needed for project B will be released at the end of six years for investment elsewhere. Perit Industries discount rate is 17%. Click here to view Exhibit 13B-1 and Exhibit 13B-2.to determine the appropriate discount factor(s) using tables Required: 1. Compute the net present value of Project A. (Enter negative values with a minus sign. Round your final answer to the nearest whole dollar amount.) 2. Compute the net present value of Project B. (Enter negative values with a minus sign. Round your final answer to the nearest whole dollar amount.) 3. Which investment alternative (if either) would you recommend that the company accept? 1. Net present value project A 2. Net present value project B 3. Which investment alternative if either) would you recommend that the company accept?
0 0
Add a comment Improve this question Transcribed image text
Answer #1
use discount factor at 17% for 6 years
1) project A
initial investment -135000
annual cash flow (25,000*3.589)= 89725
Salvage value (9,800*.390)= 3822
present value -41453 answer
2) project B
initial investment -135000
annual cash flow (63,000*3.589)= 226107
working capital realseased (135000*.390) 52650
present value 143757 answer
(use Discount factors as given in your question to get exact answer)
3) project B
Add a comment
Know the answer?
Add Answer to:
Perit Industries has $135,000 to invest. The company is trying to decide between two alternative uses...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A Project B $ 140,000 $ 0 $ 0 $140,000 $ 23,000 $ 67,000 $ 8,500 $ 0 6 years 6 years The working capital needed for project B will be released at the end...

  • Perit Industries has $130,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $130,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: 10 points Project A Project B Cost of equipment required $130,000 $ 0 Working capital investment $ 0 $130,000 required Annual cash inflows $ 21,000 $ 65,000 Salvage value of equipment in $ 8,100 $ 0 six years Life of the project 6 years 6 years eBook Hint The working capital needed for project B will be released...

  • 1 Perit Industries has $125,000 to invest. The company is trying to decide between two alternative...

    1 Perit Industries has $125,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A $125,000 $ 0 $ 23,000 $ 8,900 6 years Project B $ $125,000 $ 71,000 $ 0 6 years The working capital needed for project B will be released at the end of...

  • Perit Industries has $125,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $125,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Project A Project B $125,000 $ $ 23,000 8,900 6 years 0 $125,000 $71,000 $ 6 years Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in aix years Life of the project 0 0 The working capital needed for project B will be released at the end of six years for...

  • Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A $140,000 $ 0 $ 23,000 $ 8,500 6 years Project B $ 0 $140,000 $ 67,000 $ 0 6 years The working capital needed for project B will be released at the end of...

  • Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $140,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A Project B $140,000 $ 0 $ $140,000 $ 23,000 $ 35,000 $ 8,400 $ 0 6 years 6 years The working capital needed for project B will be released at the end of six...

  • Perit Industries has $100,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $100,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A Project B $100,000 $ $ 0 $100,000 $ 21,000 $ 16,000 $ 8,000 $ 0 6 years 6 years The working capital needed for project B will be released at the end of six...

  • Perit Industries has $100,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $100,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are Project A Project B Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project $100,000 $ 0 $100,000 $ 16,000 0 $21,000 $ 8,000 $ б уеars 6 уеars The working capital needed for project B will be released at the end of six years for...

  • Perit Industries has $190,000 to invest. The company is trying to decide between two alternative uses...

    Perit Industries has $190,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A Project B $190,000 $ 0 $ 0 $190,000 $ 28,000 $ 48,000 $ 8,900 $ 0 6 years 6 years The working capital needed for project will be released at the end of six...

  • Perit Industries has $120,000 to invest. The company is trying to decide between two alternative uses of the funds. The...

    Perit Industries has $120,000 to invest. The company is trying to decide between two alternative uses of the funds. The alternatives are: Cost of equipment required Working capital investment required Annual cash inflows Salvage value of equipment in six years Life of the project Project A Project B $120,000 $ 0 $ 0 $120,000 $ 22,000 $ 70,000 $ 8,800 $ 6 years 6 years The working capital needed for project B will be released at the end of six...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT