Question

Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows:

Activity Pools Cost Pool Total Cost Driver
Repair and maintenance on assembly machine $ 104,000 Number of units produced
Programming cost 168,000 Number of programming hours
Software inspections 12,000 Number of inspections
Product testing 16,000 Number of tests
Total overhead cost $ 300,000


Expected activity for each product follows:

Number of Units Number of Programming Hours Number of Inspections Number of Tests
Decoder P 16,000 2,000 190 1,400
Decoder Q 36,000 1,500 60 1,100
Total 52,000 3,500 250 2,500


Assume that before shifting to activity-based costing, Snowden Industries allocated all overhead costs based on direct labor hours. Direct labor data pertaining to the two decoders follow:

Direct Labor Hours
Decoder P 8,000
Decoder Q 16,000
Total 24,000

Required

  1. Compute the amount of overhead cost allocated to each type of decoder when using direct labor hours as the allocation base.

Allocated Cost
Decoder P
Decoder Q
Total
  1. Determine the cost per unit for overhead when using direct labor hours as the allocation base and when using ABC.

Cost per unit
Method Decoder P Decoder Q
ABC
Labor hours
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answers

  • Requirement A

Allocated Cost

Decoder P

$100,000

($300000/24000) x 8000 DLHs

Decoder Q

$200,000

($300000/24000) x 16000 DLHs

Total

$300,000

  • Cost per unit

Cost per unit

Method

Decoder P

Decoder Q

ABC

$                        9.13

$                    4.28

Labor hours

$                 6.25

$                    5.56

--Working for ABC

Activity Pools

Cost Pool Total

Cost Driver

Total Cost driver

Allocation Rate

Repair and maintenance on assembly machine

$104,000

Number of units produced

52000

$                                 2.00

Programming cost

$168,000

Number of programming hours

3500

$                               48.00

Software inspections

$12,000

Number of inspections

250

$                               48.00

Product testing

$16,000

Number of tests

2500

$                                 6.40

Total overhead cost

$300,000

Decoder P

Decoder Q

Activity Pools

Allocation Rate

No. of cost driver

Overhead allocated

No. of cost driver

Overhead allocated

Repair and maintenance on assembly machine

$                         2.00

16000

$                        32,000.00

36000

$      72,000.00

Programming cost

$                       48.00

2000

$                        96,000.00

1500

$      72,000.00

Software inspections

$                       48.00

190

$                          9,120.00

60

$        2,880.00

Product testing

$                         6.40

1400

$                          8,960.00

1100

$        7,040.00

Total Allocated Cost

$                      146,080.00

Total Allocated Cost

$   153,920.00

Allocated Cost

Decoder P

$146,080

Decoder Q

$153,920

Total

$300,000

Add a comment
Know the answer?
Add Answer to:
Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $ 113,900 145,600 12,000 16,000 $287,500 Cost Driver Number of units...

  • Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $117,500 150,500 20,000 24,000 $312,000 Cost Driver Number of units produced...

  • Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity- based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $104,000 168,000 12,000 16,000 $300,000 Cost Driver Number of units...

  • Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 61,600 Number of units produced Programming cost 88,920 Number of programming hours Software inspections 7,260 Number of...

  • The answer to A is also NOT 1,000,000 and 2,000,000. Snowden Industries produces two electronic decoders,...

    The answer to A is also NOT 1,000,000 and 2,000,000. Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity- based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total...

  • Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 87,000 Number of units produced Programming cost 96,000 Number of programming hours Software inspections 5,880 Number of...

  • Terry Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Terry Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follow. Activity Pools Cost Pool Total Cost Driver   Repair and maintenance on assembly machine $ 71,500   Number of units produced   Programming cost 88,920   Number of programming hours   Software inspections 6,900   Number of...

  • Rundle Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Rundle Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 110,200 Number of units produced Programming cost 95,600 Number of programming hours Software inspections 9,240 Number of...

  • Rooney Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Rooney Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $ 90, 100 102,500 6,960 11,780 $ 211,340 Cost Driver Number...

  • Munoz Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Munoz Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $100,700 89,280 6,240 11,880 $208,100 Cost Driver Number of units produced...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT