a) Overhead cost allocated
Decoder P | Decoder Q | |
Overhead cost allocated | 287500/23000*6900 = 86250 | 201250 |
b) Overhead cost per unit
When using direct labor hour
Decoder P | Decoder Q | |
Overhead cost allocated | 287500/23000*6900 = 86250 | 201250 |
Unit | 20100 | 46900 |
Overhead cost per unit | 4.29 | 4.29 |
When using ABC
Decoder P | Decoder Q | |
Repairs and maintenance of assembly machine | 113900/67000*20100 = 34170 | 79730 |
Programming cost | 145600/4000*2300 = 83720 | 61880 |
Software inspection | 12000/300*228 = 9120 | 2880 |
Product testing | 16000/2000*1120 = 8960 | 7040 |
Total Overhead | 135970 | 151530 |
Unit | 20100 | 46900 |
Overhead cost per unit | 6.76 | 3.23 |
Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...
Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 104,000 Number of units produced Programming cost 168,000 Number of programming hours Software inspections 12,000 Number of...
Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $117,500 150,500 20,000 24,000 $312,000 Cost Driver Number of units produced...
Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity- based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $104,000 168,000 12,000 16,000 $300,000 Cost Driver Number of units...
Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 61,600 Number of units produced Programming cost 88,920 Number of programming hours Software inspections 7,260 Number of...
Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 87,000 Number of units produced Programming cost 96,000 Number of programming hours Software inspections 5,880 Number of...
Rundle Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 110,200 Number of units produced Programming cost 95,600 Number of programming hours Software inspections 9,240 Number of...
Rooney Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $ 90, 100 102,500 6,960 11,780 $ 211,340 Cost Driver Number...
Munoz Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $100,700 89,280 6,240 11,880 $208,100 Cost Driver Number of units produced...
Terry Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follow. Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 71,500 Number of units produced Programming cost 88,920 Number of programming hours Software inspections 6,900 Number of...
The answer to A is also NOT 1,000,000 and 2,000,000. Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity- based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total...