Question

Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming a

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Overhead cost allocated

Decoder P Decoder Q
Overhead cost allocated 287500/23000*6900 = 86250 201250

b) Overhead cost per unit

When using direct labor hour

Decoder P Decoder Q
Overhead cost allocated 287500/23000*6900 = 86250 201250
Unit 20100 46900
Overhead cost per unit 4.29 4.29

When using ABC

Decoder P Decoder Q
Repairs and maintenance of assembly machine 113900/67000*20100 = 34170 79730
Programming cost 145600/4000*2300 = 83720 61880
Software inspection 12000/300*228 = 9120 2880
Product testing 16000/2000*1120 = 8960 7040
Total Overhead 135970 151530
Unit 20100 46900
Overhead cost per unit 6.76 3.23
Add a comment
Know the answer?
Add Answer to:
Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 104,000 Number of units produced Programming cost 168,000 Number of programming hours Software inspections 12,000 Number of...

  • Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $117,500 150,500 20,000 24,000 $312,000 Cost Driver Number of units produced...

  • Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity- based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $104,000 168,000 12,000 16,000 $300,000 Cost Driver Number of units...

  • Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 61,600 Number of units produced Programming cost 88,920 Number of programming hours Software inspections 7,260 Number of...

  • Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Benson Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 87,000 Number of units produced Programming cost 96,000 Number of programming hours Software inspections 5,880 Number of...

  • Rundle Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Rundle Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Cost Pool Total Cost Driver Repair and maintenance on assembly machine $ 110,200 Number of units produced Programming cost 95,600 Number of programming hours Software inspections 9,240 Number of...

  • Rooney Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Rooney Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $ 90, 100 102,500 6,960 11,780 $ 211,340 Cost Driver Number...

  • Munoz Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Munoz Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total $100,700 89,280 6,240 11,880 $208,100 Cost Driver Number of units produced...

  • Terry Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires...

    Terry Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity-based costing to allocate overhead costs. It has identified four activity pools. Relevant information follow. Activity Pools Cost Pool Total Cost Driver   Repair and maintenance on assembly machine $ 71,500   Number of units produced   Programming cost 88,920   Number of programming hours   Software inspections 6,900   Number of...

  • The answer to A is also NOT 1,000,000 and 2,000,000. Snowden Industries produces two electronic decoders,...

    The answer to A is also NOT 1,000,000 and 2,000,000. Snowden Industries produces two electronic decoders, P and Q. Decoder P is more sophisticated and requires more programming and testing than does Decoder Q. Because of these product differences, the company wants to use activity- based costing to allocate overhead costs. It has identified four activity pools. Relevant information follows: Activity Pools Repair and maintenance on assembly machine Programming cost Software inspections Product testing Total overhead cost Cost Pool Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT