Solution a:
Lansing Inc. | |||
Particulars | Physical units | Equivalent units | |
Prior Department | Department T | ||
Flow of units: | |||
Units to be accounted for: | |||
Beginning WIP inventory | 15000 | ||
Units started this period | 35000 | ||
Total units to account for | 50000 | ||
Units accounted for: | |||
Completed and transferred out | 45000 | 45000 | 45000 |
Units in ending inventory | 5000 | ||
Prior department | 5000 | ||
Department T | 1000 | ||
Total units accounted for | 50000 | 50000 | 46000 |
Lansing Inc. | |||
Particulars | Total | Equivalent units | |
Prior Department | Department T | ||
Flow of costs: | |||
Costs to be accounted for: | |||
Costs in beginning inventory | $169,150.00 | $116,000.00 | $53,150.00 |
Current period costs | $489,050.00 | $280,000.00 | $209,050.00 |
Total costs to be accounted for | $658,200.00 | $396,000.00 | $262,200.00 |
Cost per equivalent unit: | |||
Prior department | $7.92 | ||
Department T | $5.70 | ||
Costs accounted for: | |||
Costs assigned to units transferred out | $612,900.00 | $356,400.00 | $256,500.00 |
Costs of ending inventory | $45,300.00 | $39,600.00 | $5,700.00 |
Total costs accounted for | $658,200.00 | $396,000.00 | $262,200.00 |
Lansing, Inc. provides the following information for one of its department's operations for June (no new...
Lansing, Inc. provides the following Information for one of its department's operations for June (no new material is added in Department T). $ WIP inventory-Department T Beginning inventory ((8,480 units, 20% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (19,300 units started) Prior department costs Department T costs 38, 390 7,480 94,578 145,928 The ending Inventory has 3,400 units, which are 50 percent complete with respect to Department T costs...
Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T). WIP inventory-Department T Beginning inventory (8,600 units, 208 complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (19,700 units started) Prior department costs Department costs $ 41,030 11, 110 100, 470 198.240 The ending inventory has 3,600 units, which are 50 percent complete with respect to Department T costs...
Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T). $ WIP inventory-Department T Beginning inventory (8,500 units, 30% complete with respect to Department I costs) Transferred-in costs (from Department 5) Department T conversion costs Current work (19,500 units started) Prior department costs Department T costs 39,700 15,190 97,500 168,350 The ending inventory has 3,500 units, which are 60 percent complete with respect to Department T costs and...
Lansing, Inc. provides the following Information for one of its department's operations for June (no new material is added in Department T). $ WIP inventory-Department T Beginning inventory (9,880 units, 25% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (20,5ee units started) Prior department costs Department T costs 46.550 15,700 112,750 207.ese The ending Inventory has 4,000 units, which are 50 percent complete with respect to Department T costs and...
Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T): WIP inventory- Department T Beginning inventory (7,800 units, 25% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (18,100 units started) Prior department costs Department T costs 30,950 11,200 77,830 157,850 The ending inventory has 2,800 units, which are 50 percent complete with respect to Department T costs and...
Please give explanation on how to get highlighted numbers. Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T): WIP inventory—Department T Beginning inventory (15,000 units, 60% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (35,000 units started) Prior department costs Department T costs $ 116,000 53,150 280,000 209,050 The ending inventory has 5,000 units, which are 20...
Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is added in Department T): WIP inventory—Department T Beginning inventory ((8,700 units, 20% complete with respect to Department T costs) Transferred-in costs (from Department S) $ 42,380 Department T conversion costs 10,338 Current work (19,900 units started) Prior department costs 103,480 Department T costs 190,350 The ending inventory has 3,700 units, which are 60 percent complete with respect to Department T costs and...
Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is added in Department T). WIP inventory—Department T Beginning inventory (8,200 units, 20% complete with respect to Department T costs) Transferred-in costs (from Department S) $ 35,830 Department T conversion costs 8,930 Current work (18,900 units started) Prior department costs 88,830 Department T costs 167,020 The ending inventory has 3,200 units, which are 50 percent complete with respect to Department T costs and...
Exercise 8-41 (Static) Prepare a Production Cost Report: FIFO Method (LO 8-2, 4, 5) Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is added in Department T). WIP inventory—Department T Beginning inventory (15,000 units, 60% complete with respect to Department T costs) Transferred-in costs (from Department S) $ 116,000 Department T conversion costs 53,150 Current work (35,000 units started) Prior department costs 280,000 Department T costs 209,050 The ending inventory has...
Lansing, Inc. provides the following information for one of its department's operations for June (no new materials is added in Department T): WIP Inventory - Department T Beginning inventory (8,500 units, 30% complete with respect to Department T costs) Transferred-in costs (from Department S) $39,700 Department T conversion costs 15,190 Current work (19,500 units started) Prior department costs 97,500 Department T costs 168,350 The ending inventory has 3,500 units, which are 60 percent complete with respect to Department T costs...