Question

Lansing, Inc. provides the following Information for one of its departments operations for June (no new material is added in

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Physical Units Equivalent Units
Prior Department Department T
Flow of Units:
Units to be accounted for:
   Beginning WIP Inventory 8400
   Units started this period 19300
Total Units to be accounted for 27700
Units Accounted for:
Completed and transferred out 24300 24300 24300
Units in ending inventory 3400
Prior department 3400
Department T 1700
Total Units accounted for 27700 27700 26000
Total Prior Department Department T
Flow of costs:
Cost to be accounted for:
   Cost in Beginning WIP Inventory $45,870 $38,390 $7,480
   Current Period costs $2,40,490 $94,570 $1,45,920
Total Cost to be accounted for $2,86,360 $1,32,960 $1,53,400
Cost per Equivalent
   Prior Department $4.80
   Department T $5.90
Costs Accounted for:
   Cost assigned to units transferred out (respective Equivalent units*Cost per Equivalent unit) $2,60,010 $1,16,640 $1,43,370
   Cost of ending WIP inventory (respective units*Cost) $26,350 $16,320 $10,030
Total Costs accounted for $2,86,360 $1,32,960 $1,53,400
Add a comment
Know the answer?
Add Answer to:
Lansing, Inc. provides the following Information for one of its department's operations for June (no new...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lansing, Inc. provides the following information for one of its department's operations for June (no new...

    Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T): WIP inventory-Department T Beginning inventory (15,000 units, 60% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (35,000 units started) Prior department costs Department T costs $ 116,000 53,150 280,000 209,050 The ending inventory has 5,000 units, which are 20 percent complete with respect to Department T costs and...

  • Lansing, Inc. provides the following information for one of its department's operations for June (no new...

    Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T). WIP inventory-Department T Beginning inventory (8,600 units, 208 complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (19,700 units started) Prior department costs Department costs $ 41,030 11, 110 100, 470 198.240 The ending inventory has 3,600 units, which are 50 percent complete with respect to Department T costs...

  • Lansing, Inc. provides the following information for one of its department's operations for June (no new...

    Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T). $ WIP inventory-Department T Beginning inventory (8,500 units, 30% complete with respect to Department I costs) Transferred-in costs (from Department 5) Department T conversion costs Current work (19,500 units started) Prior department costs Department T costs 39,700 15,190 97,500 168,350 The ending inventory has 3,500 units, which are 60 percent complete with respect to Department T costs and...

  • Lansing, Inc. provides the following Information for one of its department's operations for June (no new...

    Lansing, Inc. provides the following Information for one of its department's operations for June (no new material is added in Department T). $ WIP inventory-Department T Beginning inventory (9,880 units, 25% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (20,5ee units started) Prior department costs Department T costs 46.550 15,700 112,750 207.ese The ending Inventory has 4,000 units, which are 50 percent complete with respect to Department T costs and...

  • Lansing, Inc. provides the following information for one of its department's operations for June ...

    Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T): WIP inventory- Department T Beginning inventory (7,800 units, 25% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (18,100 units started) Prior department costs Department T costs 30,950 11,200 77,830 157,850 The ending inventory has 2,800 units, which are 50 percent complete with respect to Department T costs and...

  • Lansing, Inc. provides the following information for one of its department’s operations for June (no new...

    Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is added in Department T): WIP inventory—Department T Beginning inventory ((8,700 units, 20% complete with respect to Department T costs) Transferred-in costs (from Department S) $ 42,380 Department T conversion costs 10,338 Current work (19,900 units started) Prior department costs 103,480 Department T costs 190,350 The ending inventory has 3,700 units, which are 60 percent complete with respect to Department T costs and...

  • Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is add...

    Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is added in Department T). WIP inventory—Department T Beginning inventory (8,200 units, 20% complete with respect to Department T costs) Transferred-in costs (from Department S) $ 35,830 Department T conversion costs 8,930 Current work (18,900 units started) Prior department costs 88,830 Department T costs 167,020 The ending inventory has 3,200 units, which are 50 percent complete with respect to Department T costs and...

  • Lansing, Inc. provides the following information for one of its department's operations for June (no new...

    Lansing, Inc. provides the following information for one of its department's operations for June (no new materials is added in Department T): WIP Inventory - Department T Beginning inventory (8,500 units, 30% complete with respect to Department T costs) Transferred-in costs (from Department S) $39,700 Department T conversion costs 15,190 Current work (19,500 units started) Prior department costs 97,500 Department T costs 168,350 The ending inventory has 3,500 units, which are 60 percent complete with respect to Department T costs...

  • Lansing, Inc. provides the following information for one of its department’s operations for June (no new...

    Lansing, Inc. provides the following information for one of its department’s operations for June (no new material is added in Department T): WIP inventory—Department T Beginning inventory ((7,800 units, 25% complete with respect to Department T costs) Transferred-in costs (from Department S) $ 30,950 Department T conversion costs 11,200 Current work (18,100 units started) Prior department costs 77,830 Department T costs 157,850 The ending inventory has 2,800 units, which are 50 percent complete with respect to Department T costs and...

  • Please give explanation on how to get highlighted numbers. Lansing, Inc. provides the following information for...

    Please give explanation on how to get highlighted numbers. Lansing, Inc. provides the following information for one of its department's operations for June (no new material is added in Department T): WIP inventory—Department T Beginning inventory (15,000 units, 60% complete with respect to Department T costs) Transferred-in costs (from Department S) Department T conversion costs Current work (35,000 units started) Prior department costs Department T costs $ 116,000 53,150 280,000 209,050 The ending inventory has 5,000 units, which are 20...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT