Question

Question 9: Consider the following cash flow profile and assume MARR is 10%/year. 0 1 L End of Year Cash Flow -50 18 18 18 18
0 0
Add a comment Improve this question Transcribed image text
Answer #1

A. As per Descartes rule the IRR of the project is one. That is the given project cash flow has only one sign change thus the IRR is only one.

B. Nordstrom criterion suggests that there is only single sign change in the cumulative cash flow therefore, there is a unique IRR.

C. The net present worth of the project is

NPW = -50 + 18(P/A, 1%,6)

Assume rate to be 25%

NPW = -50 + 18(P/A,25%.6)

NPW = - 50 + 18 × 2.9514

NPW = 3.125632

Now assume rate to be 28%

NPW = -50 + 18(P/A,28%.6)

NPW = - 50 + 18 × 2.759379

NPW = - 0.331164

Now apply linear interpolation 3.125632 IRR = 25+ (28 – 25) * 3.125632 – (-0.331164)

IRR = 25 + 3 × 0.9041

IRR = 25 + 2.70

IRR = 27.70%

IRR is greater than MARR thus the project is beneficial.

D. First convert the cash inflow into future value

FW = 18(F/A,10%,6)

FW = 18 × 7.71561

FW = 138.88098

The present value of the cash outflow = $ 50

50(1 + ERR) = 138.88098

(1+ ERR) = 138.88098 50

(1 + ERR = 2.7776196

1+ ERR = 2.77761966

ERR = 1.18562 - 1

ERR = 0.18562

\large \implies ERR= 18.56 \%

The ERR is greater than MARR thus this project is beneficial.

Please contact if having any query will be obliged to you for your generous support. Please help me it mean a lot to me. Thank you.

Add a comment
Know the answer?
Add Answer to:
Question 9: Consider the following cash flow profile and assume MARR is 10%/year. 0 1 L...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 10: Consider the following cash flow profile and assume MARR is 12%/year. 0 1 2...

    Question 10: Consider the following cash flow profile and assume MARR is 12%/year. 0 1 2 3 End of Year Cash Flow -1000 3400 -5700 3800 a. What does Descartes' rule of signs tell us about the IRR (8) of this project? b. What does the Norstrom's criterion tell us about the IRR (s) of this project? c. Determine the ERR for this project. Is this project economically attractive?

  • There are two additional parts to a and b Question 8 Consider the following cash flow...

    There are two additional parts to a and b Question 8 Consider the following cash flow profile and assume MARR is 15%/yr. EOY NCF 0$75 $21 $21 $21 $21 5 $21 6 $21 Click here to access the TVM Factor Table Calculator. Part a What does Descartes' rule of signs tell us about the IRR(s) of this project? Click if you would like to Show Work for this question: Show LINK TO TEXT LINK TO TEXT LINK TO VIDEO Attempts:...

  • Given the following cash flow, what does Descartes’ Rule tell us about the IRRs of this...

    Given the following cash flow, what does Descartes’ Rule tell us about the IRRs of this project? EOY Net CF There are 3 possible IRRs 0 -10,000 There are 2 possible IRRs 1 2,000 There is 1 possible IRR 2 4,000 There are 0 IRRs 3 -5500 A and B 4 6000 A and C 5 4000 None of the above – you must solve for the IRR

  • NPV profile of a project Given the following cash flow of Project L-2, draw the NPV...

    NPV profile of a project Given the following cash flow of Project L-2, draw the NPV profile. Hint Be sure to use a discount rate of zero for one intercept (y-axis) and solve for the IRR for the other intercept (x-axis). Year 0-$260,000 Year 1 $45,000 Year 2 $80,000 Year 3 $119,000 Year 4 $132,000 What is the NPV of Project L-2 where zero is the discount rate? $116,000 Round to the nearest dollar.) What is the IRR of Project...

  • NPV profile of a project. Given the following cash flow of Project L-2, draw the NPV...

    NPV profile of a project. Given the following cash flow of Project L-2, draw the NPV profile. Hint: Be sure to use a discount rate of zero for one intercept (y-axis) and solve for the IRR for the other intercept (x-axis). (Click on the following icon in order to copy its contents into a spreadsheet.) Year 0 = - $290,000 Year 1 = $44,000 Year 2 = $75,000 Year 3 = $116,000 Year 4 = $140.000 What is the NPV...

  • NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV...

    NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV profile. Hint​: Be sure to use a discount rate of zero for one intercept ​(y​-axis) and solve for the IRR for the other intercept ​(x​-axis). ​ Year 0​ = -$240,000 Year 1​ = $ 40,000 Year 2​ = $ 79,000 Year 3​ = $ 118,000 Year 4​ = $ 131,000 What is the NPV of Project​ L-2 where zero is the discount​ rate?

  • marr 13% the MARR is 12% Consider the following investment projects: 1 AC DE 0-1500-2000-2100-1000 1...

    marr 13% the MARR is 12% Consider the following investment projects: 1 AC DE 0-1500-2000-2100-1000 1 3000 1560 2800 3600 2-1500 944 -200 -5700 3 15 0 0 100 a) For each project, apply the sign rule to predict the number of possible IRR's b) Classify each project as either a simple or a non-simple investment. c) For each project, plot the NPW profile as a function of i between 0 and 120%. d) For each project, compute the value(s)...

  • Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...

    Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$ 360,000 –$ 45,000 1 35,000 23,000 2 55,000 21,000 3 55,000 18,500 4 430,000 13,600    Whichever project you choose, if any, you require a return of 14 percent on your investment. c-1 What is the NPV for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)       c-2 If you apply the NPV...

  • DO 5.75 PLEASE 5.71 Consider the following cash flow of a certain project: Net Cash Flow...

    DO 5.75 PLEASE 5.71 Consider the following cash flow of a certain project: Net Cash Flow n 0 -$2000 1 800 2 900 3 If the project's IRR is 10%, (a) Find the value of X. (b) Is this project acceptable at MARR = 8%? 5.75 Recent technology has made possible a computerized vending machine that . grind coffee beans and brew fresh coffee on demand. The computer also makes can possible such complicated functions as changing $5 and $10...

  • is). NPV profile of a project. Given the following cash flow of Project L-2 draw the...

    is). NPV profile of a project. Given the following cash flow of Project L-2 draw the NPV profile. Hint. Be sure to use a discount rate of zero for one interceptaxis) and solve for the IRR for the other intercept (Click on the following on in order to copy its contents into a spreadsheet) Year 0 -$300.000 Year 1 $43,000 Year 2 - $75.000 Year $110,000 Year 4 $135.000 What is the NPV of Project L-2 where zero is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT