Problem 9-2 After-Tax Cost of Debt

LL Incorporated's currently outstanding 8% coupon bonds have a yield to maturity of 13%. LL believes it could issue new bonds at par that would provide a similar yield to maturity. If its marginal tax rate is 35%, what is LL's after-tax cost of debt? Round your answer to two decimal places.______ %

Problem 9-5 Cost of Equity: Dividend Growth

Summerdahl Resort's common stock is currently trading at $33.00 a share. The stock is expected to pay a dividend of $1.75 a share at the end of the year (D1 = $1.75), and the dividend is expected to grow at a constant rate of 5% a year. What is the cost of common equity? Round your answer to two decimal places.________%

Problem 9-6 Cost of Equity: CAPM

Booher Book Stores has a beta of 1.2. The yield on a 3-month T-bill is 4.5% and the yield on a 10-year T-bond is 6.5%. The market risk premium is 6%, and the return on an average stock in the market last year was 12.5%. What is the estimated cost of common equity using the CAPM? Round your answer to two decimal places.____ %

Problem 9-8 WACC

David Ortiz Motors has a target capital structure of 40% debt and 60% equity. The yield to maturity on the company's outstanding bonds is 12%, and the company's tax rate is 40%. Ortiz's CFO has calculated the company's WACC as 11.29%. What is the company's cost of equity capital? Round your answer to two decimal places.______ %

Problem 10-01 NPV

A project has an initial cost of $45,125, expected net cash inflows of $10,000 per year for 9 years, and a cost of capital of 8%. What is the project's NPV? (Hint: Begin by constructing a time line.) Do not round your intermediate calculations. Round your answer to the nearest cent. $______

Problem 10-02 IRR

A project has an initial cost of $60,000, expected net cash inflows of $14,000 per year for 9 years, and a cost of capital of 12%. What is the project's IRR? Round your answer to two decimal places.________ %

Problem 10-03 MIRR

A project has an initial cost of $43,425, expected net cash inflows of $12,000 per year for 10 years, and a cost of capital of 8%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.______%

Problem 10-04 Profitability Index

A project has an initial cost of $61,000, expected net cash inflows of $12,000 per year for 11 years, and a cost of capital of 9%. What is the project's PI? Do not round your intermediate calculations. Round your answer to two decimal places. ________

Problem 10-05 Payback

A project has an initial cost of $59,050, expected net cash inflows of $13,000 per year for 8 years, and a cost of capital of 13%. What is the project's payback period? Round your answer to two decimal places._______ years

Problem 10-06 Discounted Payback

A project has an initial cost of $60,000, expected net cash inflows of $14,000 per year for 7 years, and a cost of capital of 13%. What is the project's discounted payback period? Round your answer to two decimal places.________ years

Please remember to round your answer to two decimal places.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 9-2 = After tax cost of debt = 8.45%

Reason -

After tax cost of debt = Yield to maturity * ( 1 - tax rate )

= 13% * ( 1 - 0.35 )

= 13% * 0.65

= 8.45%

As per HOMEWORKLIB RULES first question has been answered with reason. For answers to subsequent questions, please post them separately. Thank you.

Add a comment
Know the answer?
Add Answer to:
Please remember to round your answer to two decimal places. Problem 9-2 After-Tax Cost of Debt...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT