We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 93,400 units per year. Price per unit is $38.73, variable cost per unit is $23.85, and fixed costs are $854,000 per year. The tax rate is 23 percent, and we require a return of 10 percent on this project. |
|
a. | Calculate the base-case operating cash flow and NPV. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) |
b. | What is the sensitivity of NPV to changes in the sales figure? (Do not round intermediate calculations and round your answer to 3 decimal places, e.g., 32.161.) |
c. | If there is a 450-unit decrease in projected sales, how much would the NPV change? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
d. | What is the sensitivity of OCF to changes in the variable cost figure? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) |
e. | If there is a $1 decrease in estimated variable costs, how much would the OCF change? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) |
SEE THE IMAGE. ANY DOUBTS, FEEL FREE TO ASK. THUMBS UP PLEASE
We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage...
We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 93,400 units per year. Price per unit is $38.73, variable cost per unit is $23.85, and fixed costs are $854,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 93,400 units per year. Price per unit is $38.73, variable cost per unit is $23.85, and fixed costs are $854,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $2,010,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,400 units per year. Price per unit is $38.61, variable cost per unit is $23.75, and fixed costs are $848,000 per year. The tax rate is 21 percent, and we require a return of 10 percent on this project. a. Calculate the base-case operating cash flow...
We are evaluating a project that costs $1,180,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 88,100 units per year. Price per unit is $34.80, variable cost per unit is $21.05, and fixed costs are $761,000 per year. The tax rate is 40 percent, and we require a return of 10 percent on this project Calculate the base-case operating cash flow and...
We are evaluating a project that costs $1.980.000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89.100 units per year. Price per unit is $38.55. variable cost per unit is $23.70, and fixed costs are $845.000 per year. The tax rate is 25 percent, and we require a return of 10 percent on this project. a. Calculate the base-case operating cash flow...
We are evaluating a project that costs $2,160,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,900 units per year. Price per unit is $38.91, variable cost per unit is $24.00, and fixed costs are $863,000 per year. The tax rate is 21 percent, and we require a return of 11 percent on this project. a. Calculate the base-case operating cash flow...
We are evaluating a project that costs $1,800,000, has a 6-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,300 units per year. Price per unit is $38.19, variable cost per unit is $23.40, and fixed costs are $827,000 per year. The tax rate is 24 percent, and we require a return of 9 percent on this project. a. Calculate the base-case operating cash flow...
We are evaluating a project that costs $2,130,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,600 units per year. Price per unit is $38.85, variable cost per unit is $23.95, and fixed costs are $860,000 per year. The tax rate is 25 percent, and we require a return of 11 percent on this project. 0:45 a. Calculate the base-case operating cash...
We are evaluating a project that costs $2,280,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 98,300 units per year. Price per unit is $39.15, variable cost per unit is $24.20, and fixed costs are $875,000 per year. The tax rate is 25 percent, and we require a return of 11 percent on this project. a. Calculate the base-case operating cash flow...
We are evaluating a project that costs $1,710,000, has a 6-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 86,400 units per year. Price per unit is $38.01, variable cost per unit is $23.25, and fixed costs are $818,000 per year. The tax rate is 21 percent, and we require a return of 9 percent on this project. points Skipped eBook a. Calculate the base-case...