Solution
Budgeted Production for July = 7900 Units
Direct Labor Hours per unit = 0.40
Total Direct Labor Hour = 7900 x 0.40 = 3160
Labor cost per hour = $5.10
Therefore, Budgeted Labor Cost = 3160 Hours x $5.10 = $16,116
Answer: Option (d) $16,116
For July, White Corporation has budgeted production of 7,900 units. Each unit requires 0.40 direct labor-hours...
For July, White Corporation has budgeted production of 6,000 units. Each unit requires 0.10 direct labor-hours at a cost of $8.50 per direct labor-hour. How much will White Corporation budget for labor in July $51,000 $5,160 $600 $5,100
Tora Co plans to produce 1,070 units in July. Each unit requires three hours of direct labor. The direct labor rate is $20 per hour. Prepare a direct labor budget for July TORA CO. Direct Labor Budget For Month Ended July 31 Budget production (units) 1,070 units Total labor hours needed Budgeted direct labor cost
Tora Co plans to produce 1,100 units in July. Each unit requires four hours of direct labor. The direct labor rate is $15 per hour. Prepare a direct labor budget for July 05 TORA CO. Direct Labor Budget For Month Ended July 31 points Budget production units) Total labor hours needed Budgeted Grect labor cost
Flagstaff Company has budgeted production units of 9,200 for July and 9,400 for August. The direct labor requirement per unit is 0.40 hours. Labor is paid at the rate of $19 per hour. The total cost of direct labor for the month of August is: Multiple Choice $69,920. $3,760. $71,440. $3,680. $141,360.
Zhang Industries budgets production of 210 units in June and 220 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate if $12.20 per hour. The indirect labor rate is $19.20 per hour. Compute the budgeted direct labor cost for July.
Depasquale Corporation is working on its direct labor budget for the next two months. Each unit of output requires 0.51 direct labor-hours. The direct labor rate is $8.20 per direct labor hour. The production budget calls for producing 5,100 units in May and 5,500 units in June. If the direct labor work force is fully adjusted to the total direct labor-hours needed each month, what would be the total combined direct labor cost for the two months? Multiple Choice $23.001.00...
Zhang Industries budgets production of 250 units in June and 260 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate is $13.00 per hour. The indirect labor rate is $20.00 per hour. Compute the budgeted direct labor cost for July. Multiple Choice $7,500. $4,875. $7,800. $5,070. $12,870.
Zhang Industries budgets production of 390 units in June and 400 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate is $15.80 per hour. The indirect labor rate is $22.80 per hour. Compute the budgeted direct labor cost for July. Multiple Choice $13,338. $9,243. $13,680. $9,480. $23,160.
A manufacturing company has budgeted production at 940 units for the month. Each unit requires 3.5 hours of labor to produce. The average labor rate is $15 per hour. The total cost of direct labor for the month will be?
Each unit requires 4 pounds of direct materials, which cost $5 per pound. The company's policy is to maintain direct materials inventory equal to 40% of the next month's direct materials requirement. As of June 30, the company has 7,520 pounds of direct materials in inventory, which complies with the policy. Prepare a direct materials budget for July. MIAMI SOLAR Direct Materials Budget 4,700 4 For Month Ended July 31 Budget production (units) Materials requirements per unit Materials needed for...