Question

Current Designs CD9 Diane Buswell is preparing the 2020 budget for one of Current Designs rotomolded Extensive meetings with

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Production Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total Quarter 1
Unit Sales                1,000                1,500                   750                   750                4,000        1,100
Plus: Desired ending inventory                   300                   150                   150                   220                   220            300
Less: Beginning Inventory                   200                   300                   150                   150                   200            220
Units to produce                1,100                1,350                   750                   820                4,020        1,180
2 Direct Materials Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total Quarter 1
Polythene
Units to be produced                1,100                1,350                   750                   820                4,020        1,180
Multiply by: Quantity of DM needed per unit                      54                      54                      54                      54                      54              54
Total Quantity of DM needed              59,400              72,900              40,500              44,280            217,080      63,720
Plus: Desired Ending inventory of DM              18,225              10,125              11,070              15,930              15,930
Less: Beginning inventory of DM              14,850              18,225              10,125              11,070              14,850
Total Quantity of DM to purchase              62,775              64,800              41,445              49,140            218,160
Multiply by: Cost per unit                  1.50                  1.50                  1.50                  1.50                  1.50
Total cost of DM Purchases              94,163              97,200              62,168              73,710            327,240
Finishing Kit
Total Quantity of DM needed                1,100                1,350                   750                   820                4,020
Multiply by: Cost per unit              170.00              170.00              170.00              170.00              170.00
Total cost of DM Purchases            187,000            229,500            127,500            139,400            683,400
3 Direct Labour Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total
Type I
Units to be produced                1,100                1,350                   750                   820                4,020
Multiply by: DL hours per unit                        2                        2                        2                        2                        2
Total DL hours                2,200                2,700                1,500                1,640                8,040
Multiply by: DL Rate                      15                      15                      15                      15                      15
Total Direct Labour budget              33,000              40,500              22,500              24,600            120,600
Type II
Units to be produced                1,100                1,350                   750                   820                4,020
Multiply by: DL hours per unit                        3                        3                        3                        3                        3
Total DL hours                3,300                4,050                2,250                2,460              12,060
Multiply by: DL Rate                      12                      12                      12                      12                      12
Total Direct Labour budget              39,600              48,600              27,000              29,520            144,720
Total Type I + II              72,600              89,100              49,500              54,120            265,320
4 Manufacturing Overhead Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total
150% of Labour Cost            108,900            133,650              74,250              81,180            397,980
5 Selling and Admin Expense Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total
Budgeted Sales in units                1,000                1,500                   750                   750                4,000
Cost/ unit sold                      45                      45                      45                      45                      45
Sub Total              45,000              67,500              33,750              33,750            180,000
Fixed Expenses                7,500                7,500                7,500                7,500              30,000
Toyal Selling and Admin Expenses              52,500              75,000              41,250              41,250            210,000
Add a comment
Know the answer?
Add Answer to:
Current Designs CD9 Diane Buswell is preparing the 2020 budget for one of Current Designs' rotomolded...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT