1) Overhead rate :
Department D = 770000/1100000 = 70% of direct labor cost
Department E = 1500000/125000 = 12 per direct labor hour
Department K = 780000/120000 = 6.50 per machine hour
2) Total manufacturing cost
Department D (210000+180000+180000*70%) | 516000 |
Department E (189000+165000+16500*12) | 552000 |
Department K (117000+56250+10480*6.50) | 241370 |
3) Calculate overhead
Department D (126000-148500) | 22500 Under applied |
Department E (198000-186000) | 12000 over applied |
Department K (68120-118500) | 50380 under applied |
Problem 15-04A Agassi Company uses a job order cost system in each of its three manufacturing...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $770,000 $1,500,000 $780,000 Direct labor costs $1,100,000 $1,875,000 $675,000 Direct labor hours 150,000 125,000 60,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $770,000 $1,500,000 $780,000 Direct labor costs $1,100,000 $1,875,000 $675,000 Direct labor hours 150,000 125,000 60,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $924,000 $1,500,000 $900,000 Direct labor costs $1,320,000 $1,875,000 $675,000 Direct labor hours 150,000 125,000 60,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments, Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $990,000 $1,237,500 150,000 600,000 $1,750,000 $1,875,000 125,000 750,000 $1,080,000 $675,000...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $924,000 $1,500,000 $900,000 Direct labor costs $1,320,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $924,000 $1,500,000 $900,000 Direct labor costs $1,320,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D к so Manufacturing overhead Direct labor costs Direct labor hours Machine hours $854,000 $1,220,000...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...