Compute the total manufacturing costs assigned to jobs in
January in each department. (Round answers to 0 decimal
places, e.g. 2,500.)
Manufacturing Costs |
||
Department D | $ | |
Department E | $ | |
Department K | $ |
Calculation of Total manufacturing costs
Total manufacturing costs= Direct materials+Direct labor+Manufacturing overhead applied
Department D= $210000+180000+(180000*70%)= $516000
Department E= $189000+165000+(16500*$12)= $552000
Department K= $117000+56250+(10440*$7.50)= $251550
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $924,000 $1,500,000 $900,000 Direct labor costs $1,320,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D к so Manufacturing overhead Direct labor costs Direct labor hours Machine hours $854,000 $1,220,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $924,000 $1,500,000 $900,000 Direct labor costs $1,320,000 $1,875,000 $675,000 Direct labor hours 150,000 125,000 60,000...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments, Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $854,000 $1,220,000 150,000 600,000 $1,500,000...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $770,000 $1,500,000 $780,000 Direct labor costs $1,100,000 $1,875,000 $675,000 Direct labor hours 150,000 125,000 60,000...
Problem 15-04A Agassi Company uses a job order cost system in each of its three manufacturing departments Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $770,000 $1,100,000 150,000 600,000 $1,500,000 $1,875,000 125,000 750,000...