Question

Question 1 Swifty Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BPrepare a schedule showing the computations of the activity-based overhead rates per cost driver. Activity Cost Pools EstimatPrepare a schedule assigning each activitys overhead cost to the two products. Activity Cost Pools BC113 Estimated Use of Co

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity cost pools Estimated overhead Estimated use of cost driver per activity Activity-based overhead rates
Machine setup $17,500 35 setups $500 per setup
Machining 120,750 4,830 machine hours 25 per machine hour
Packing 28,670 470 orders 61 per order
$166,920
BC113 AD908
Activity cost pools Estimated use of cost driver per product Activity-based overhead rates Cost assigned Estimated use of cost driver per product Activity-based overhead rates Cost assigned
Machine setup 20 $500 $10,000 15 $500 $7,500
Machining 1,140 25 28,500 3,690 25 92,250
Packing 120 61 7,320 350 61 21,350
Total assigned cost $45,820 $121,100
BC113 AD908
Overhead cost per unit $22.91 ($45,820/2,000) $121.1 ($121,100/1,000)
Add a comment
Know the answer?
Add Answer to:
Question 1 Swifty Industries has three activity cost pools and two products. It estimates production 2,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Overhead $17,500 120,750 28,670 Activity Cost Pools Machine setup Machining Packing 20 Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Activity Cost Pools Machine setup Machining Packing Cost Drivers Setups Machine hours Orders Estimated Overhead $14,800 78,560 27,030 Estimated Use of Cost Drivers per Product Estimated Use...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...

  •    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units...

       Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $18,500 106,920 35,640 Cost Drivers Setups Machine hours...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers BC113 AD908 per Activity Estimated Overhead Activity Cost Pools Cost Drivers Machine setup...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $22,000 97,200 30,080 Cost Drivers Setups Machine hours Orders 21 Estimated Use of Cost Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Prod...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Please solve the questions in the boxes, much appreciated! thank you so much!! Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 un...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Annual Overhead Data Estimated Overhead $18,500 106,920 35,640 Drivers per Activity Activity Cost Pools Machine setup Machining...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each . pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Product AD908 Annual Overhead Data Estimated Activity Cost Pools Cost Drivers Overhead Machine setup Setups $22,000 Machining Machine hours 97,200 Packing Orders 30,080 Estimated Use of Cost Drivers per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT