Question

Required information Greenwood Co uses a plantwide overhead rate based on direct labor hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z mpany manufactures two products 15,000 units of Product Y and 7000 units of Product Z. The company Estimat ed Overhead Expected Activity Activity Cost Poo1 Activity Measur Machining Machine setups Production design Number of products General factory Cost s221,100 s 107,100 85, 000 11,000 MHs Machine-hours Number of setups 210 setups 2 products Direct labor-hours 251,000 10,000 DLH Product Y Produet 2 Activity Measure Machining Number or setupa Number of products Direct 1abor-hours 8,100 50 2,900 160 8, 100 1,900 3. What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.) per MH Iivity rate

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total Cost of Machining = $221,100

Expected activity = 11,000 Machine Hours

Activity Rate = Total Overhead Cost/Expected Level of Activity

= $221,100/11,000

= $20.1 per Machine Hour

Add a comment
Know the answer?
Add Answer to:
Required information Greenwood Co uses a plantwide overhead rate based on direct labor hours. It is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z Estimated Overhead Cost s 221,100 Expected ActivitY Activity Cost Pool Machining Machine setups Production...

  • Required information Greenwood Company manufactures two products -15,000 units of Product Y and 7000 units of...

    Required information Greenwood Company manufactures two products -15,000 units of Product Y and 7000 units of Product uses a plantwide overhead rate based on direct labor-hours. It is considering implementin UASRC I system that allocates all of its manufacturing overhead to four cost pools. The followirig g an activity-based costing information is available for the company as a whole and for Products Y and Z Estimated Overhead Act tivity Cost Pool Activity MeasureCost Expected ActivitY Machining Machine setups Production design...

  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7000 units of Product...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and z Estimated Overhead Cost s 221,100 s 107, 100 85,000 Activity Cost Pool Expected ivity...

  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7000 units of Product...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z Estimated Overhead Expected ActivitY Activity Measure Machine-hours Number of setups Number of products Direct...

  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • A. what is the companys plantwide iverhead rate ? B.how much manufacturing overhead is allocated to...

    A. what is the companys plantwide iverhead rate ? B.how much manufacturing overhead is allocated to product Y and product Z? C. what is the actuvity rate for the machining activity cost pool? D.what is the activity rate for the machine setups activity cost pool? E. what is the activity rate fir the product design activity cost pool? F. what is the activity rate for the general factory cost pool? Greenwood Company manufactures two products—14,000 units of Product Y and...

  • Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates

    Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $788,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost PoolActivity MeasureEstimated Overhead CostExpected ActivityMachiningMachine-hours$ 238,80012,000MHsMachine setupsNumber of setups$ 93,100190setupsProduct designNumber of products$ 83,0002productsGeneral...

  • Required information Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product...

    Required information Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Estimated Overhead Cost Expected Activity 12,000 MHs 130 setups 2 products 15,000 DLHS Activity...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z Estimated Overhead Expected Activity 11,000 MHs Activity Cost Pool Machining Machine setups Production design...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT