Required: | |||
1- Using the data provided below you are to input formulas in the area designated below to calculate: % complete, revenue to be recognized in each year, and gross profit to be recognized in each year. (10 points) | |||
Hint: I suggest you use formulas with an IF function regarding the gross profit section of your speadsheet because your spreadsheet should be able to calculate correct answers whether a contract generates a profit or loss. | |||
2- Using the data given and the solutions your spreadsheet generated, prepare all journal entries for 2020. Whevenver possible, the amounts for your journal entries should be formulas that reference the appropriate cells in the calcuations below. (10 points) | |||
3-Once you have completed the spreadsheet save your file with your last name(s) and first name(s) and upload it under Assignments by the assignment due date. | |||
Data: | |||
Contract price | 1,200,000 | ||
2019 | 2020 | 2021 | |
Costs incurred to date** | $280,000 | $600,000 | $785,000 |
Estimated costs yet to be incurred | 520,000 | 200,000 | 0 |
Customer billings to date** | 250,000 | 500,000 | 1,200,000 |
Collections of billings to date** | 120,000 | 320,000 | 1,040,000 |
**Hint: You have to figure out the actual cost, billings, and collections for each respective year. The information presented is "to date" not "Costs expended this year" as in the handouts and some of your assigned exercises/problems. | |||
Use the format provided below to input formulas for each respective year. | |||
2019 | 2020 | 2021 | |
Costs expended to date | |||
Estimated total costs | |||
% complete | |||
Contract price | |||
% complete | |||
Revenue recognized to date | |||
Revenue recognized prior | |||
Revenue recognized current | |||
Estimated total gross profit | |||
% complete | |||
Gross profit recognized to date | |||
Gross profit recognized prior | |||
Gross profit recognized current |
Answer-1:
2019 | 2020 | 2021 | |
Costs expended to date | 2,80,000 | 6,00,000 | 7,85,000 |
Estimated total costs | 8,00,000 | 8,00,000 | 7,85,000 |
% complete | 35% | 75% | 100% |
Contract price | 12,00,000 | 12,00,000 | 12,00,000 |
% complete | 35% | 75% | 100% |
Revenue recognized to date | 4,20,000 | 9,00,000 | 12,00,000 |
Revenue recognized prior | - | 4,20,000 | 9,00,000 |
Revenue recognized current | 4,20,000 | 4,80,000 | 3,00,000 |
Estimated total Gross profit | 4,15,000 | 4,15,000 | 4,15,000 |
% complete | 35% | 75% | 100% |
Gross profit recognized to date | 140,000 | 300,000 | 4,15,000 |
Gross profit recognized prior | - | 140,000 | 300,000 |
Gross profit recognized current | 140,000 | 160,000 | 115,000 |
Answer-2:
Required: 1- Using the data provided below you are to input formulas in the area designated...
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $820,500 $1,077,000 Estimated costs to complete 585,800 273,500 –0– Billings to date 297,000 894,000 1,580,000 Collections to date 273,000 816,000 1,419,000 Instructions: Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each...
During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...
Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date Estimated costs to complete $410,000 $901,180 $1,067,000 590,000 197,820 -O- 297,000 903,000 1,590,000 271,000 805,000 1,434,000 Billings to date Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used....
Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction is scheduled to commence 1 July 2018 and the estimated date of completion is 30 June 2021. The cost of the building is estimated to be $155m and the total contract price is fixed at $180m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $’000 $’000 $’000 Costs to date 46,500 108,500 155,000 Estimated Costs...
During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...