Question

TB MC Qu. 1-133 At an activity level of.. A n activity level of 9.00 machine hours in a month, Fakes Corporations total vari
0 0
Add a comment Improve this question Transcribed image text
Answer #1

​​​Option C is the correct answer

765310 1 Kariable cost per unit = - 9100 = 84.1 per unit ($) Fixed cost per unit at 9700 units 224 070 = 23.1 p.() 9700 TotalHIT THE LIKE BUTTON

Add a comment
Know the answer?
Add Answer to:
TB MC Qu. 1-133 At an activity level of.. A n activity level of 9.00 machine...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • At an activity level of 9,200 machine-hours in a month, Falks Corporation's total variable production engineering...

    At an activity level of 9,200 machine-hours in a month, Falks Corporation's total variable production engineering cost is $825,240 and its total fixed production engineering cost is $249,100. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 9,400 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.)

  • At an activity level of 8,500 machine-hours in a month, Falks Corporation's total variable production engineering...

    At an activity level of 8,500 machine-hours in a month, Falks Corporation's total variable production engineering cost is $708,900 and its total fixed production engineering cost is $168,210. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 8,900 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.)

  • At an activity level of 9,100 machine-hours in a month, Nooner Corporation's total variable production engineering...

    At an activity level of 9,100 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $803,530 and its total fixed production engineering cost is $161,280. What would be the total production engineering cost per unit, both fixed and variable, at an activity level of 9,600 machine-hours in a month? Assume that this level of activity is within the relevant range. (Do not round intermediate calculations.)

  • 5. At an activity level of 9,100 machine-hours in a month, Nooner Corporation's total variable production...

    5. At an activity level of 9,100 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $803,530 and its total fixed production engineering cost is $161,280. What would be the total production engineering cost per unit, both fixed and variable, at an activity level of 9,600 machine-hours in a month? Assume that this level of activity is within the relevant range. (Do not round intermediate calculations.)

  • At an activity level of 9,900 machine-hours in a month, Falks Corporation's total variable production engineering...

    At an activity level of 9,900 machine-hours in a month, Falks Corporation's total variable production engineering cost is $882,090 and its total fixed production engineering cost is $196,000. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 10,000 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.) Multiple Choice $107.81 $108.88 $108.70 $108.35

  • At an activity level of 9,500 machine-hours in a month, Falks Corporation’s total variable production engineering...

    At an activity level of 9,500 machine-hours in a month, Falks Corporation’s total variable production engineering cost is $779,950 and its total fixed production engineering cost is $200,970. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 9,900 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.)

  • TB MC Qu. 2-133 Lupo Corporation uses a job-order costing ... 13 Lupo Corporation uses a...

    TB MC Qu. 2-133 Lupo Corporation uses a job-order costing ... 13 Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine hours. The company based its predetermined overhead rate for the current year on the following data: 303 points 8 023525 Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 32,300 $581,400 $ 2 Print Recently, Job T687 was completed with the following characteristics 10 40 Number of units...

  • TB MC Qu. 2-133 (Algo) Lupo Corporation uses a job-order... Lupo Corporation uses a job-order costing...

    TB MC Qu. 2-133 (Algo) Lupo Corporation uses a job-order... Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour Recently, Job T687 was completed with the following characteristics: 30,400 $425,600 $ 5 10 Number of units in the job Total machine-hours Direct materials Direct labor...

  • TB MC Qu. 5-46 The Macon Company uses the high-low... The Macon Company uses the high-low...

    TB MC Qu. 5-46 The Macon Company uses the high-low... The Macon Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: Machine Hours 20,000 8,000 Busiest month (June) Slowest month (December) Direct Labor Costs $250,000 $ 127,000 If Macon expects to use 14,500 machine hours next month, what are the estimated direct labor costs? O $172,000. O $179,125. $193,625. $148,625. O The Missou Manufacturing Company recorded overhead costs of $14,202...

  • TB MC Qu. 7-67 Feldpausch Corporation has provided the following... Feldpausch Corporation has provided the following...

    TB MC Qu. 7-67 Feldpausch Corporation has provided the following... Feldpausch Corporation has provided the following data from its activity-based costing system Activity Cost Pool Assembly Processing orders Total Cost Total Activity $1,137,360 84,000 machine-hours $ 28,479 1,100 orders inspection- $ 97,155 1,270 hours Inspection The company makes 470 units of product W268 a year, requiring a total of 660 machine-hours, 50 orders, and 40 inspection-hours per year. The product's direct materials cost is $40.30 per unit and its direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT