Question

1. The ________ considers the project's risk relative to the firm overall risk. A. The Objective...

1. The ________ considers the project's risk relative to the firm overall risk.

A. The Objective Approach

B. The Pure Pay Approach

C. The Subjective Approach

D. The Bottom-Up Approach

2. ________ are not tax deductible, so there is no tax impact on the cost of equity.

A. Interest expenses

B. Director's remuneration

C. Dividends

D. All of the above

3. ________ itself is a non-cash expense and it is only relevant because it affects taxes.

A. Depreciation expense

B. Interest expense

C. Capital gain

D. Both A and C

4. Which of the following is correct about Average Accounting Return

A. Reject the project if the ARR is less than a preset rate

B. Accept the project if the ARR is large than IRR

C. Accept the project if the ARR is greater than a preset rate

D. ARR must be equal to a preset rate for the acceptance of a project

5. What is the disadvantage of Payback method?

A. Difficult to understand

B. No adjustment for uncertainty of later cash flows

C. Ignores the time value of money

D. Biased again short-term project

6. Which of the following statement is true about Net Present Value decision rule?

A. If the NPV is negative, reject the project

B. A negative NPV mean the project will increase the wealth of the owners

C. If value of the NPV means the amount of value created for the firm

D NPV rule does not account for the time value of money

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1)
Subject approach uses project's risk relative to the firms overall risks.
If the project risk is higher than the firms risk than the discount rate for the project
is higher than the firm's WACC.
If the project risk is lower than the firms risk than the discount rate for the project
is lower than the firm's WACC.
Hence the option (C) is correct.
2)
Dividends are paid to shareholder's which are not tax deductible.
Therefore there is no tax impact on the cost of equity
Hence the option (C) is correct.
3)
Depreciation expense is a non cash expense which reduces the income from
operations and hence the taxable income.
Thus the option (A) is correct.
4)
Projects with accounting rate of return higher than the required rate of return should be accepted.
Hence the option (C) is correct.
5)
Payback period is when the intial investment is fully recovered.
The cash flows after the full recovery of cash flows donot affect the patback period.
Hence the option (B) is correct.
Add a comment
Know the answer?
Add Answer to:
1. The ________ considers the project's risk relative to the firm overall risk. A. The Objective...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1) Suppose that you calculate the NPV of a project, and obtain a value of $100...

    1) Suppose that you calculate the NPV of a project, and obtain a value of $100 million dollars. After completing your analysis, you find out that the corporate tax rate will change from 40% to 30%. If nothing else changes, what is the effect of this tax change on the NPV you had calculated? Assume that your company has no debt. a) The new NPV will be lower than $100 b) The new NPV will be higher than $100 c)...

  • You calculate the net present value (NPV) for a project your firm is considering. Using a...

    You calculate the net present value (NPV) for a project your firm is considering. Using a 12% discount rate, the NPV is $600,000. The cost of the project is $1,200,000. What decision do you make? Group of answer choices Reject because the NPV is less than the cost of the project. Accept because $600,000 divided by $1,200,000 is 50%, which is greater than the discount rate. None of these are correct. Reject because the NPV should be negative. Accept because...

  • You calculate the net present value (NPV) for a project your firm is considering. Using a...

    You calculate the net present value (NPV) for a project your firm is considering. Using a 12% discount rate, the NPV is $600,000. The cost of the project is $1,200,000. What decision do you make? Group of answer choices Accept because the NPV is greater than $0. Reject because the NPV should be negative. None of these are correct. Reject because the NPV is less than the cost of the project. Accept because $600,000 divided by $1,200,000 is 50%, which...

  • ​Which one of the following statements is correct?

    Question 5Which one of the following statements is correct? 1) The payback period ignores the time value of money. 2) A longer payback period is preferred over a shorter payback period. 3) The payback rule states that you should accept a project if the payback period is less than one year. 4) The payback rule is biased in favor of long-term projects. 5) The payback period considers the timing and amount of all of a project's cash flows. Question 6A firm has $6 Billion in debt...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time Cash Flow 0 1 2 3 4 5 6 -1,150 30570770770 370770 Use the NPV decision rule to evaluate this project, should it be accepted or rejected? Multiple Choice 0...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0123 Project -35,000 25,000 45,000 16,000 A Cash Flow Project -45,000 25,000 35,000 B Cash Flow Use the NPV decision rule to evaluate these projects; which one(s) should...

  • Consider an investment with an immediate outflow of $5,000 followed by annual inflows of $1,500 for the next four years....

    Consider an investment with an immediate outflow of $5,000 followed by annual inflows of $1,500 for the next four years. If the firm has a 10% cost of capital, what is the project’s NPV and should they accept the project? a. NPV = $1,000; accept the project b. NPV = -$245; accept the project c. NPV = $1,000; reject the project d. NPV = -$245; reject the project Which of the following is NOT a potential pitfall of using the...

  • Professor Wendy Smith has been offered the following​ opportunity: A law firm would like to retain...

    Professor Wendy Smith has been offered the following​ opportunity: A law firm would like to retain her for an upfront payment of $49,000. In​ return, for the next year the firm would have access to eight hours of her time every month. As an alternative payment​ arrangement, the firm would pay Professor​ Smith's hourly rate for the eight hours each month. ​ Smith's rate is $545 per hour and her opportunity cost of capital is 15% per year. What does...

  • If a firm applies its overall firm's beta to projects with varying levels of risk, the...

    If a firm applies its overall firm's beta to projects with varying levels of risk, the firm will tend to: a. accept all low risk projects b. accept only projects of equal risk to its current operations c. become riskier over time d. reject the riskiest projects e. remain at its current level of overall risk

  • 1. Whenever there is a conflict between NPV and another decision rule, you should always use...

    1. Whenever there is a conflict between NPV and another decision rule, you should always use NPV. A. True B. False 2. ________ finds one or more companies that specialize in the product or service that we are considering. A. The Objective Approach B. The Pure Play Approach C. The Subjective Approach D. None of the above 3. The required return of bond is best estimated by computing the ________ on the bond. A. Yield-to-maturity B. market value C. Risk...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT