Workings for Answer 15:
Calculation of manufacturing overhead rate:
Job 843 Job 641 Total Note
Work in Process     18,000.00
Less:
Direct Materials      6,000.00 3,000.00        9,000.00
Direct Labor      4,000.00 2,000.00        6,000.00 B
Manufacturing overhead        3,000.00 C
Manufacturing overhead rate 50.00% D=C/B
Answer 15 Amount $
Estimated Manufacturing overhead      65,000.00 E
Manufacturing overhead rate 50.00% See D
Estimated Direct Labor 130,000.00 F=E/D
Answer 16 Amount $
Actual Manufacturing overhead      66,500.00
Less: Estimated Manufacturing overhead      65,000.00
Under applied Manufacturing overhead        1,500.00 G
As the Manufacturing overhead is under applied so if adjusted to COGS it will increase and adjusted COGS will be:
Amount $
Unadjusted COGS 411,000.00
Add: Under applied Manufacturing overhead        1,500.00 See G
Adjusted COGS 412,500.00
SO answer is option B.
Add a comment
Know the answer?
Add Answer to:
Use the information below to answer the following question 15 and 16 ac is a manufacturering...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the information below to answer the following two questions: Jenn Brothers has two manufacturing departments-Production...

    Use the information below to answer the following two questions: Jenn Brothers has two manufacturing departments-Production and Finishing. At the beginning of the most recent period, the company made the following estimates related to production and manufacturing overhead: Estimated machine-hours (MH) Estimated direct labor-hours (DLH) Estimated total manufacturing overhead (MOH) Production 17.000 5,085 S 159.800 Finishing 10,000 3.215 64.300 S At the end of the period, results for two jobs the company started and completed were as follows: Job A55...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT