13 | PLANT WIDE OVERHED RATE(POHR) | ||||||
A | Total Manufacturing Overhead | $224,100 | (159800+64300) | ||||
B | Total Machine Hour | 27000 | (17000+10000) | ||||
C=A/B | Plant wide Overhead Rate(POHR) | $8.30 | |||||
Cost of Job A55: | |||||||
Total Machine hours used=90+20 | 110 | ||||||
Applied Overhead =110*$8.30 | $913.00 | ||||||
Cost of Job A55: | |||||||
a | Direct Material Cost | $482.00 | |||||
b | Direct Labor Cost | $549.00 | |||||
c | Manufacturing Overhead | $913.00 | |||||
d=a+b+c | Total Cost of Job A55 | $1,944.00 | |||||
ANSWER: | |||||||
C,$1,944.00 | |||||||
14 | PRODUCTION DEPARTMENT RATE | ||||||
a | Total Overhead in Production Dept | $159,800 | |||||
b | Total Machine hours in Production Dept | 17000 | |||||
c=a/b | Production Dept Overhead Rate | $9.40 | |||||
FINISHING DEPARTMENT RATE | |||||||
d | Total Overhead in Finishing Dept | $64,300 | |||||
e | Total Direct labor hours(DLH) in Finishing Dept | 3215 | |||||
f=d/e | Finishing Dept Overhead Rate | $20.00 | |||||
Cost of Job B72: | |||||||
g | Direct Material Cost | $514.00 | |||||
h | Direct Labor Cost | $671.00 | |||||
i | Applied Overhead in Production Dept | $1,034.00 | (110*9.40) | ||||
j | Applied Overhead in Finishing Dept | $280.00 | (14*20.00) | ||||
k=i+j | Total Manufacturing Overhead | $1,314.00 | |||||
l=g+h+k | Total Cost of Job B72 | $2,499.00 | |||||
ANSWER: | |||||||
B. $2,499.00 | |||||||
Use the information below to answer the following two questions: Jenn Brothers has two manufacturing departments-Production...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining 2,000 $ 2,400 $ 2.10 Finishing 8,000 $ 64,000 $ 6.00 Total 10,000 $ 66,400 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 4,000 6,000 $ 5,200 $ 20,400 $ 1.50 $ 6.00 Total 10,000 $ 25,600 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 5,000 5,000 $ 6,500 $ 29,500 $ 2.00 $ 4.00 Total 10,000 $ 36,000 During the most recent month, the company started and completed two jobs-- Job B and Job K. There were no beginning inventories....
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 9,000 8,000 17,000 Estimated total fixed manufacturing overhead cost $ 18,000 $ 7,800 $ 25,800 Estimated variable manufacturing overhead cost per MH $ 2.70 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 8,400 $ 11,700 $ 20,100 Estimated variable manufacturing overhead cost per MH $ 3.00 $ 5.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MS) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs Job B and Job K. There were no beginning inventories....
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MH) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Machining Finishing 6,000 5,000 $ 5,100 $ 39,200 $ 1.40 $ 2.00 Total 11,000 $ 44,300 During the most recent month, the company started and completed two jobs-Job B and Job K. There were no beginning inventories. Data...