Exercise 22-8 Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is avaPace Corporation has requested an estimate to rebuild its spot welder. Second Chance estimates that it would require 41 hours

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a.
Calculation of rate charged per hour of labor
Total time charges $334,400.00
Budgeted repair time 7600
Labor rate $44.00
Profit margin on labor cost $35.00
Labor rate charged per hour $79.00 (44+35)
b.
Calculation of material loading percentage
Material loading percentage 19.642% 79157/403000
Profit margin on parts 26.000%
Material loading percentage 45.642%
c.
Calculation of total estimated bill
Time charges $3,239.00 41*79
Material loading % $1,049.76 2300*45.642%
Cost of parts $2,300.00
Total estimated bill $6,588.76
Add a comment
Know the answer?
Add Answer to:
Need help with this question! Exercise 22-8 Second Chance Welding rebuilds spot welders for manufacturers. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance. Time Charges Material Loading Charges Technicians' wages and benefits $237,000 - Parts manager's salary and benefits - $39,100 Office employee's salary and benefits 71,100 9,169 Other overhead 39,500 19,300 Total budgeted costs $347,600 $67,569 The company desires a $34.00 profit margin per hour of labor and a 21.00% profit margin on parts. It has budgeted for 7,900 hours of repair...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Second Chance. Material Loading Time Charges Charges $192,400 Technicians' wages and benefits $39,600 Parts manager's salary and benefits Office employee's salary and benefits 51,800 9.400 Other overhead 14,800 19,600 Total budgeted costs $259,000 $68.600 The company desires a $39 profit margin per hour of labor and a 27.00% proft margin on parts. It has budgeted for 7,400 hours of repair time in...

  • Exercise 8-8 (Video) Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data...

    Exercise 8-8 (Video) Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Second Chance. Time Charges $198,800 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 56,800 7,100 $262,700 $39,800 9,700 28,000 $77,500 - The company desires a $35 profit margin per hour of labor and a 23.00% profit margin on parts. It has budgeted for 7,100 hours...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is availa...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Second Chance. Time Charges $238,000 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 49,000 35,000 $322,000 $40,100 7,430 27.440 $74,970 The company desires a $37 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7,000 hours of repair time in...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance. Material Loading Charges Charges Time Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhcad Total budgeted costs 192,400 44,400 266,4007515 $40,600 7,321 600 27230 The company desires a $34.00 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7,400 hours of repair time in the...

  • Sheridan Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available...

    Sheridan Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Sheridan. Time Charges Material Loading Charges Technicians' wages and benefits $221,200 -        Parts manager's salary and benefits -        $40,200 Office employee's salary and benefits 39,500 6,840 Other overhead 23,700 23,040 Total budgeted costs $284,400 $70,080 The company desires a $37 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7,900 hours of repair time in...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance. Exercise 22-8 (Part Level Submission) Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance Time Charges $229,100 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 55,300 31,600 $316,000 $40,500 10,735 20,450 $71,685 The company desires...

  • Bonita Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available...

    Bonita Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Bonita Time Charges $237,000 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 71.100 39,500 $347.600 $39,100 8,900 19,200 $67,200 The company desires a $34 profit margin per hour of labor and a 21.00% profit margin on parts. It has budgeted for 7,900 hours of repair time in the coming...

  • Blackboard + →XCIO Question 31 Second Chance Welding rebuilds spot welders for manufacturers. The following bolted...

    Blackboard + →XCIO Question 31 Second Chance Welding rebuilds spot welders for manufacturers. The following bolted cont data for 2017 is valable for Second Chance Material Time Leading Charges Charges Technicians wages and $175.000 benefits Parts manager's $39,000 salary and benefits Office employee's 28.000 6,600 salary and benefits Other 19.000 overhead Total budgeted $210,000 $64,600 costs 7,000 The company desires a $30.00 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7.000...

  • Blackboard + →XCIO Question 31 Second Chance Welding rebuilds spot welders for manufacturers. The following bolted...

    Blackboard + →XCIO Question 31 Second Chance Welding rebuilds spot welders for manufacturers. The following bolted cont data for 2017 is valable for Second Chance Material Time Leading Charges Charges Technicians wages and $175.000 benefits Parts manager's $39,000 salary and benefits Office employee's 28.000 6,600 salary and benefits Other 19.000 overhead Total budgeted $210,000 $64,600 costs 7,000 The company desires a $30.00 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7.000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT