Question

Calculate the Economic Value Added (EVA) for a project with $1,000,000 in capital invested where the...

Calculate the Economic Value Added (EVA) for a project with $1,000,000 in capital invested where the Return on Capital is 16% and the Cost of Capital is 8%

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:

Nopat = return on capital * capital invested = 16% * $1,000,000 = $160,000

cost of capital = 8%

capital = $1,000,000

EVA = Nopat - (cost of capital * capital)

EVA = $160,000 - (8% * $1,000,000)

EVA = $160,000 - $80,000

EVA = $80,000

hence the economic value added is $80,000

Add a comment
Know the answer?
Add Answer to:
Calculate the Economic Value Added (EVA) for a project with $1,000,000 in capital invested where the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT