Question

cn 15 Mw (18 pts) Help Save & 2 Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 In December 2016. Shiee Computers management establishes the 2017 predetermined overhead rate based on direct lsbor cost The Information used in setting this rate includes estimates that the company will Incur $747500 ot overhead costs and $575,000 of direct abor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1 What is the predetermined overhead rate for 20177 2Using the informasion on the following job cost sheet, determine the total cost of the job. Complete this question by entering your answers in the tabs below Required 1 Required 2 Using the information on the following job cost sheet, determine the total cost of the jotb. Drect Matris Direct Laber No. Amount Coests MacBook Pro 2 3 45 67 8 90 0
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Predetermined Overhead rate = 130%

Working: Estimated overhead costs / Estimated direct labor = Overhead rate

747,500 / 575,000 = 130%

2) Solution: Total cost of the job: $22,710

Working:

Direct materials

Direct labor

Overheads

Date

Req No.

Amount

Time Ticket No.

Amount

Costs applied

Total cost

Mar-05

4-129

5,000

T-306

700

910

6,610

Mar-11

4-142

7,020

T-432

1,250

1625

9,895

Mar-18

4-167

3,330

4-456

1,250

1625

6,205

15,350

3,200

4,160

22,710

Add a comment
Know the answer?
Add Answer to:
cn 15 Mw (18 pts) Help Save & 2 Exercise 15-11 Overhead rate; costs assigned to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 Shire Computer's predetermined overhead rate is...

    Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $636,000 of overhead costs and $530,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by...

  • Check my wc Exercise 02-11 Overhead rate; costs assigned to jobs LO P3 1.42 points Shire...

    Check my wc Exercise 02-11 Overhead rate; costs assigned to jobs LO P3 1.42 points Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $747.500 of overhead costs and $575,000 of direct labor cost for the year. During March, Shire began and completed Job 13:56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the...

  • Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 Shire Computer's predetermined overhead rate is based on di...

    Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $708,000 of overhead costs and $590,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the Information on the following Job cost sheet to determine the total cost of the job. > Answer is not...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $728,000 of overhead costs and $520,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • in December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    in December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job No. 13-56, 1) What is the predetermined overhead rate for 2017? 2) Use the information on the following job cost sheet to determine the total cost of Job...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $832,000 of overhead costs and $520,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $767,000 of overhead costs and $590,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor...

    In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2015. During March 2015, Shire began and completed Job No. 13-56. 1. What is the predetermined overhead rate for year 2015? Overhead Rate 1 Choose Denominator: Choose Numerator: II Overhead Rate Overhead rate / 11 1 II...

  • I need both required parts In December 2016, Shire Computer's management establishes the 2017 predetermined overhead...

    I need both required parts In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $714,000 of overhead costs and $510,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor co...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $812,000 of overhead costs and $580,000 of direct labor cost in year 2017. During March 2017. Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT