Part a)
Project A: Payback period:
Year | Opening Balance | Investment | CF | Closing Balance |
0 | $ 5,400.00 | $ 5,400.00 | ||
1 | $ 5,400.00 | $ 1,100.00 | $ 4,300.00 | |
2 | $ 4,300.00 | $ 1,100.00 | $ 3,200.00 | |
3 | $ 3,200.00 | $ 3,200.00 | $ - |
Project B: Payback period:
Year | Opening Balance | Investment | CF | Closing Balance |
0 | $ 1,400.00 | $ 1,400.00 | ||
1 | $ 1,400.00 | $ - | $ 1,400.00 | |
2 | $ 1,400.00 | $ 1,400.00 | $ - |
Project C: Payback period:
Year | Opening Balance | Investment | Principal repayment | Closing Balance |
0 | $ 5,400.00 | $ 5,400.00 | ||
1 | $ 5,400.00 | $ 1,100.00 | $ 4,300.00 | |
2 | $ 4,300.00 | $ 1,100.00 | $ 3,200.00 | |
3 | $ 3,200.00 | $ 3,200.00 | $ - |
We see that the Entire investment is recovered in 3 years time so that is the payback period
Part b) If cutoff is 2 years then only project 2 is acceptable
Part c) If the cutoff is 3 years then all 3 meet the criteria and can be selected, If they are mutually exclusive and therefore only one can be selected then that will be project B otherwise all can be selected
Part d-1)
Project A: NPV
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -5,400.00 | 1/(1+0.1)^0= | 1 | 1*-5400= | $ -5,400.00 |
1 | $ 1,100.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*1100= | $ 1,000.00 |
2 | $ 1,100.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*1100= | $ 909.09 |
3 | $ 3,200.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*3200= | $ 2,404.21 |
NPV = Sum of all Discounted CF | $ -1,086.70 |
Project B: NPV
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -1,400.00 | 1/(1+0.1)^0= | 1 | 1*-1400= | $ -1,400.00 |
1 | $ - | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*0= | $ - |
2 | $ 1,400.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*1400= | $ 1,157.02 |
3 | $ 2,200.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*2200= | $ 1,652.89 |
4 | $ 3,200.00 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*3200= | $ 2,185.64 |
NPV = Sum of all Discounted CF | $ 3,595.56 |
Project C: NPV
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -5,400.00 | 1/(1+0.1)^0= | 1 | 1*-5400= | $ -5,400.00 |
1 | $ 1,100.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*1100= | $ 1,000.00 |
2 | $ 1,100.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*1100= | $ 909.09 |
3 | $ 3,200.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*3200= | $ 2,404.21 |
4 | $ 5,200.00 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*5200= | $ 3,551.67 |
NPV = Sum of all Discounted CF | $ 2,464.97 |
Part d-2) Projects B and C have positive NPV
Part e) Payback period completely ignores the CF after the investment is recovered so even if it becomes negative and is a high drawback of the project, this method would suggest that this project should be accepted. Therefore the given statement is false
Cas a llars) a. What is the payback period on each of the projects? b. If...
23. Payback and NP a. What is the payback period on each of the following projects? Net Present Value and Other Investment Criteria 371 Cash Flows, Dellars Project Time: 1 5,000 1,000 000 3,000 1,000 1,000 2,000 3,000 5.000 1.000 1.000 3000 +5,000 b. Given that you wish to use the payback rule with a cutoff period of 2 years, which proj- ects would you accept e. If you use a cutoff period of 3 years, which projects would you...
Here are the expected cash flows for three projects: Project Year: 4 0 - 5,100 - 1,100 - 5,100 Cash Flows (dollars) 2 3 + 1,025 + 1,025 + 3,050 0 + 1,100 + 2,050 + 1,025 + 1,025 + 3,050 + 3,050 + 5,050 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...
Here are the expected cash flows for three projects: Project Year: IU 0 - 5,700 - 1,700 - 5,700 Cash Flows (dollars) 1 2 3 + 1,175 + 1,175 + 3,350 0 + 1,700 + 2,350 + 1,175 + 1,175 + 3,350 4 0 + 3,350 + 5,350 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If...
Here are the expected cash flows for three projects: Project Year: 2 0 - 5,300 - 1,300 - 5,300 Cash Flows (dollars) 1 + 1,075 + 1,075 + 3,150 0 + 1,300 + 2,150 + 1,075 + 1,075 + 3,150 0 + 3,150 + 5,150 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 3 4 1,250 3,500 - 6,000 - 2,000 - 6,000 1,250 2,000 1,250 +3,500 5,500 2,500 1,250 3,500 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a cutoff period of 3 years, which projects will you accept? d-1....
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 4 -5,300 -1,300 -5,300 +1,075 +1,075 +1,300 +1,075 +3,150 +2,150 +3,150 0 +3,150 +5,150 +1,075 a. What is the payback period on each of the projects? Project Payback Period years A В years C years AB C b. If you use a cutoff period of 2 years, which projects would you accept? O Project A O Project B O Project C O Project A...
Payback period Given the cash Bow of two projects A and B and using the payback period decision model, which project(s) do you accept and which project(s) do you reject if you have a three-year cutoff period for recapturing the initial cash outflow? For payback period calculations, assume that the cash flow is equally distributed over the year Cash Flow Cost Cash low year 1 Cash flow year 2 Cash flow Cash flow year 4 Cash flow year 5 Cash...
A firm is considering the following projects. Its opportunity cost of capital is 10%. Cash Flows, $ Project Time: 0 1 2 3 4 A -7,300 +1,575 +1,575 +4,150 0 B -3,300 0 +3,300 +3,150 +4,150 C -7,300 +1,575 +1,575 +4,150 +7,300 a. What is the payback period on each project? Project A - ____ years Project B - ____ years Project C - ____ years What is the discounted payback period on each project? (Round...
Calculating Payback Period and NPV Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 −$15,000 −$19,000 1 10,400 12,700 2 5,900 6,100 3 2,100 5,300 a.Suppose the company’s payback period cutoff is two years. Which of these two projects should be chosen? b.Suppose the company uses the NPV rule to rank these two projects. Which project should be chosen if the appropriate discount rate is 15 percent?
value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800 2,800 2,800 2,800 2,500 2.800 2,800 2,800 2,800 8 5.800 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV projects) O Project A O Project B O Project C O Projects A and B O Projects A and C Projects B and C O Projects A, B, and C O No project b. Calculate the payback...