value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800 2,800 2,800 2,800 2,500 2.800 2,800 2,800 2,800 8 5.800 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV projects) O Project A O Project B O Project C O Projects A and B O Projects A and C Projects B and C O Projects A, B, and C O No project b. Calculate the payback period for each project: (Round your answers to 2 decimal places. If a project never pays back, enter o. Project A Project B Project C year(s) year(s) year s)c. Which project(s) would a firm using the payback rule accept if the cutoff period were three years? Project(s) accepted d. Calculate the discounted payback for each project (Do not round intermediate calculations. Round your answers to 2 decimal places. If a project never pays back, enter (Click to select) Project A Project B Project C year(s year(s) year(s) e. Which project(s) would a firm using the discounted payback rule accept if the cutoff period were three years? Project(s) accepted (Click to select) References eBook & Resources Worksheet Difficulty: Intermediate

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2800-5600-7000 2800 28002800 CO C1 C2 C3 C4 CS OPPOURTUNITY COST 12% C) 0 C) C) 2800 2500 0 2800 2800 2800 2800 NPV 300.00 6628.71861.23 FORMULA NPV(12%,C1:35)+CO

A) Project B and C have Positive cash flow

B)

2800 5600 7000 C1 C2 C3 0 0 0 0 5800 0 Payback period for Project A Total amount of outflow i.e 2800 have been received in 1 Year 1st year Payback period for Project B 2800 in year 1 and 2800 in year 2-total outflow of-5600 2 YEAR Payback period for Project C Paid 5300 in 3 year and remaning 1700 paid in (1700/2800) 0.61 3.61 Year

C) A&B

D)

Discounted value of A B Discounted C value of B Discounted value of C 0 CO 1C1 2 C2 3 C3 4 C4 5 C5 2800 2800 0 0 0 0 5600 2800 2800 5800 2800 1,779.45 -7000 OPPOURTUNITY COST 28001 乏2,500.00 2500| 1,992.98 0.00 2800 1,779.45 28001 乏1,588.80 2,500.00 2,500.00 乏2,232.14 4,128.33 0 1,588.80 Discounted Project A Payback will not be period for able to pay Project A back Discounted Payback period for Project B Discounted Payback 4.46 year in 4 year project period for Project C 2.21 | 2500+2232.14= 4732.14 remaining 867.86 will be paid in 867.86/4128.33 recovered 6272.43 and remaining in (727.57/1500.80) 0.21

E) Project B

FORMULA TO CALCULATE PV

Add a comment
Know the answer?
Add Answer to:
value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800...

    value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800 2,800 2,800 2,800 2,500 2.800 2,800 2,800 2,800 8 5.800 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV projects) O Project A O Project B O Project C O Projects A and B O Projects A and C Projects B and C O Projects A, B, and C O No project b. Calculate the payback...

  • Consider the following projects: Cash Flows (S) -1,400 2,800 3,500 1,400 1,400 1,400 1,400 1,000 1,400...

    Consider the following projects: Cash Flows (S) -1,400 2,800 3,500 1,400 1,400 1,400 1,400 1,000 1,400 1,400 4,400 1.400 1,400 a. If the opportunity cost of capital is 10%, which project(s) have a positive NPV? Positive NPV projectis) Project A Project B ProjectC Projects A and B Projects A and C O Projects B and C Projects A, B, and C No project b. Calculate the payback period for each project: (Round your answers to 2 decimal places. If a...

  • Need help with part d. Thank you. Consider the following projects: Cash Flows (S) Project 0...

    Need help with part d. Thank you. Consider the following projects: Cash Flows (S) Project 0 -1,100 2,200 -3,250 1,100 1,100 1,100 1,100 1,100 4,100 1,100 1,100 1,100 1,100 a. If the opportunity cost of capital is 11%, which project(s) have a positive NPV? Positive NPV project(s) O ProjectA OProject B O Project c O Projects A and B O Projects A and C Projects B and C O Projects A, B, and C O No project b. Calculate the...

  • Cash Flows (5) Projecl Co -1,000 3,600 -4 bIN C2 СЗ 1,300 1,800 1,8cic 1,800 1,10%0...

    Cash Flows (5) Projecl Co -1,000 3,600 -4 bIN C2 СЗ 1,300 1,800 1,8cic 1,800 1,10%0 1,800 1.800 1,800 1 8D0 a. If the opportunity cost of capital is 10%, which pro ct(s) have a positive NPV? Positive NPV projectis) ● Project ProjectB Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate the payback period for each project (Round your answers to 2 decimal places. IT...

  • 1. You have the chance to participate in a project that produces the following cash flows:...

    1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV            $ __________. 2. Consider the following projects: Cash Flows...

  • 2. 10.00 points An investment project costs $10,000 and has annual cash flows of $2,800 for...

    2. 10.00 points An investment project costs $10,000 and has annual cash flows of $2,800 for six years. What is the discounted payback period if the discount rate is zero percent? (Enter 0 if the project never pays back. Round your answer to 2 decimal places, e.g. 32.16.) Discounted payback period years What is the discounted payback period if the discount rate is 4 percent? (Enter 0 if the project never pays back. Round your answer to 2 decimal places,...

  • A firm is considering the following projects. Its opportunity cost of capital is 10%. Cash Flows, $ Project...

    A firm is considering the following projects. Its opportunity cost of capital is 10%. Cash Flows, $ Project Time:       0         1          2          3         4    A -7,300 +1,575 +1,575 +4,150 0 B -3,300 0 +3,300 +3,150 +4,150 C -7,300 +1,575 +1,575 +4,150 +7,300 a. What is the payback period on each project? Project A - ____ years Project B - ____ years Project C - ____ years What is the discounted payback period on each project? (Round...

  • Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2...

    Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 3 4 1,250 3,500 - 6,000 - 2,000 - 6,000 1,250 2,000 1,250 +3,500 5,500 2,500 1,250 3,500 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a cutoff period of 3 years, which projects will you accept? d-1....

  • Here are the expected cash flows for three projects: Project Year: 4 0 - 5,100 -...

    Here are the expected cash flows for three projects: Project Year: 4 0 - 5,100 - 1,100 - 5,100 Cash Flows (dollars) 2 3 + 1,025 + 1,025 + 3,050 0 + 1,100 + 2,050 + 1,025 + 1,025 + 3,050 + 3,050 + 5,050 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...

  • Here are the expected cash flows for three projects: Project Year: IU 0 - 5,700 -...

    Here are the expected cash flows for three projects: Project Year: IU 0 - 5,700 - 1,700 - 5,700 Cash Flows (dollars) 1 2 3 + 1,175 + 1,175 + 3,350 0 + 1,700 + 2,350 + 1,175 + 1,175 + 3,350 4 0 + 3,350 + 5,350 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT