NPV = Present Value of Cash Inflows – Present Value of Cash Outflows
Project A: -2,800 + 2,800*PVF(12%, 1 year)
= -2,800 + 2,500.4
= -299.6
Project B: -5,600 + 2,800*PVF(12%, 1 year) +2,800*PVF(12%, 2 year)+ 5,800*PVF(12%, 3 year)+ 2,800*PVF(12%, 4 year)+ 2,800*PVF(12%, 5 year)
= $6,736.8
Project C: - 7,000 + + 2,800*PVF(12%, 1 year) +2,500*PVF(12%, 2 year) + 2,800*PVF(12%, 4 year)+ 2,800*PVF(12%, 5 year)
= 861.3
Hence, answer is Projects B and C
b.Payback period: Payback period is the period in which the initial investment is recovered
Project A: 0 (it will never pay back)
Project B: 2 years (2800+2800 = 5600)
Project C: 3.61 years (5,300 recovered in first 2 years, remaining 1700/out of 2,800 taken proportionately from 4th year)
value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800...
value 10.00 points Consider the following projects Cash Flows (S) Project Co -2,800 -5,600 -7,000 2,800 2,800 2,800 2,800 2,500 2.800 2,800 2,800 2,800 8 5.800 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV projects) O Project A O Project B O Project C O Projects A and B O Projects A and C Projects B and C O Projects A, B, and C O No project b. Calculate the payback...
Consider the following projects: Cash Flows (S) -1,400 2,800 3,500 1,400 1,400 1,400 1,400 1,000 1,400 1,400 4,400 1.400 1,400 a. If the opportunity cost of capital is 10%, which project(s) have a positive NPV? Positive NPV projectis) Project A Project B ProjectC Projects A and B Projects A and C O Projects B and C Projects A, B, and C No project b. Calculate the payback period for each project: (Round your answers to 2 decimal places. If a...
Need help with part d. Thank
you.
Consider the following projects: Cash Flows (S) Project 0 -1,100 2,200 -3,250 1,100 1,100 1,100 1,100 1,100 4,100 1,100 1,100 1,100 1,100 a. If the opportunity cost of capital is 11%, which project(s) have a positive NPV? Positive NPV project(s) O ProjectA OProject B O Project c O Projects A and B O Projects A and C Projects B and C O Projects A, B, and C O No project b. Calculate the...
2. 10.00 points An investment project costs $10,000 and has annual cash flows of $2,800 for six years. What is the discounted payback period if the discount rate is zero percent? (Enter 0 if the project never pays back. Round your answer to 2 decimal places, e.g. 32.16.) Discounted payback period years What is the discounted payback period if the discount rate is 4 percent? (Enter 0 if the project never pays back. Round your answer to 2 decimal places,...
1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV $ __________. 2. Consider the following projects: Cash Flows...
Cash Flows (5) Projecl Co -1,000 3,600 -4 bIN C2 СЗ 1,300 1,800 1,8cic 1,800 1,10%0 1,800 1.800 1,800 1 8D0 a. If the opportunity cost of capital is 10%, which pro ct(s) have a positive NPV? Positive NPV projectis) ● Project ProjectB Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate the payback period for each project (Round your answers to 2 decimal places. IT...
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 3 4 1,250 3,500 - 6,000 - 2,000 - 6,000 1,250 2,000 1,250 +3,500 5,500 2,500 1,250 3,500 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a cutoff period of 3 years, which projects will you accept? d-1....
1. value: 10.00 points An investment project costs $10,000 and has annual cash flows of $2,980 for six years. What is the discounted payback period if the discount rate is zero percent? (Enter 0 if the project never pays back. Round your answer to 2 decimal places, e.g., 32.16.) Discounted payback period years What is the discounted payback period if the discount rate is 4 percent? (Enter 0 if the project never pays back. Round your answer to 2 decimal...
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 4 -5,300 -1,300 -5,300 +1,075 +1,075 +1,300 +1,075 +3,150 +2,150 +3,150 0 +3,150 +5,150 +1,075 a. What is the payback period on each of the projects? Project Payback Period years A В years C years AB C b. If you use a cutoff period of 2 years, which projects would you accept? O Project A O Project B O Project C O Project A...
Here are the expected cash flows for three projects: Project Year: 4 0 - 5,100 - 1,100 - 5,100 Cash Flows (dollars) 2 3 + 1,025 + 1,025 + 3,050 0 + 1,100 + 2,050 + 1,025 + 1,025 + 3,050 + 3,050 + 5,050 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...