Question

Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $740. During July, prime costs added to the job tota

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Ending balance of Job 1600
Less: Prime costs added -610
Less: Beginning balance -740
Overhead applied to the job 250
2
Direct labor 152.50 =610/(1+3)
Direct materials 457.50 =152.50*3
3
Overhead rate 164% =250/152.50
Add a comment
Know the answer?
Add Answer to:
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $740. During July,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ex.04.38 Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $700. During...

    ex.04.38 Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $700. During July, prime costs added to the job totaled 5680. Of that amount, direct materials were three times as much as direct labor. The ending balance of the job was $1,500. Required: 1. What was overhead applied to the job during July? 2. What was direct materials for Job 46 for July? Direct labor? If rounding is required, round your answers to the nearest cent....

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • job order costing

    Bell Company’s fi scal year ends on June 30. The following accounts are found in its job order cost accounting system for the fi rst month of the new fi scal year. Raw Materials Inventory July 1 Beginning balance 19,000 July 31 Requisitions (a) 31 Purchases 90,400 July 31 Ending balance (b) Work in Process Inventory July 1 Beginning balance (c) July 31 Jobs completed (f) 31 Direct materials 80,000 31 Direct labor (d) 31 Overhead (e) July 31 Ending...

  • Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and...

    Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1,125 2,475 Balance, June 1 $7,875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,300 $1,300 Direct labor 1,400 3,100 Applied overhead 980 2,170 Balance, June 1 $7,680 $6,570 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $56,250 Number of moves 2,500 Engineering 142,500 Number of change orders 9,500 Other overhead 209,100 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering 165,000 Number of change orders 10,000 Other overhead 280,000 Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Beginning balance $0 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,200 Direct labor 1,700 2,900 Applied overhead 935 1,595 Balance, June 1 $7,635 $5,695 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $4,850 $1,400 Direct labor 800 2,800 Applied overhead 560 1,960 Balance, June 1 $6,210 $6,160 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT