Which of the following calculations should be performed to obtain a “Total Variance” proof total?
Budgeted cost less applied cost |
||
Actual cost less applied cost |
||
Actual cost less budgeted cost |
||
None of these is correct. |
Answer: 3rd option
This is the difference of actual cost and budgeted cost.
Suppose in case of material variance, total material variance is proved as below:
[SP = standard or budgeted price; SQ = standard of budgeted quantity; AP = actual price; AQ = actual quantity]
Material price variance = SP × AQ – AP × AQ
Material quantity variance = SQ × SP – SP × AQ
Total material variance = Material price variance + Material quantity variance
= [SP × AQ – AP × AQ] + [SQ × SP – SP × AQ]
= SP × AQ – AP × AQ + SQ × SP – SP × AQ
= SQ × SP - AP × AQ
= Budgeted cost – Actual cost
Which of the following calculations should be performed to obtain a “Total Variance” proof total? Budgeted...
QUESTION 8 In which of the following situations will the overhead volume variance be favorable? O When more units are produced than were originally planned O When actual overhead costs are less than the flexible budget When the predetermined overhead rate was set too low When there are units remaining in ending inventory QUESTION 9 Which of the following values is used in the calculations for both the controllable overh variance and the overhead volume variance? Overhead applied to production...
calculate the
1.percent scedule variance?
2.percent cost variance?
3.total scedule variance?
4. total cost variance?
M uit ve tal Cost Variance (5 points)? Planned Budget Cost/Time review as of Day 55 Planned Actual Percent Percent Duration Duration Scheduled Performed Budgeted Cost Work Performed Actual Cost Work Performed 210 Budgeted Cost Work Scheduled 240 100% 100% 100% 1009 8 100% $ . 150 $ $ $ 6 8 15 100% 400 100% 100% 100% 100% 23 $ - $ 100% 100%...
At the start of 2018, X Company developed the following budgeted total cost function: $11.64X + $219,000, where X is number of units produced. Budgeted production for the year was 10,200 units. Actual total costs and actual production in 2018 were different than the budgeted amounts. The actual total cost function turned out to be $12.28X + $198,014, and actual production was 9,300 units. What was the 2018 flexible budget variance for total fixed cost [a positive number means a...
Please find the correct Variable Overhead Rate Variance for
#3. thank you!
Norwall Company's budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing overhead is $30,624 per month The following information is available for a recent month: a. The denominator activity of 9,570 machine-hours is used to compute the predetermined overhead rate. b. At a denominator activity of 9,570 machine-hours, the company should produce 3,300 units of product. c. The company's actual operating results were:...
Exercise 21-19 Computation of total
overhead rate and total overhead variance LO P3 World Company
expects to operate at 80% of its productive capacity of 50,000
units per month. At this planned level, the company expects to use
25,000 standard hours of direct labor. Overhead is allocated to
products using a predetermined standard rate of 0.625 direct labor
hours per unit. At the 80% capacity level, the total budgeted cost
includes $50,000 fixed overhead cost and $275,000 variable overhead
cost....
Question 41 (4 points) To calculate the direct materials usage variance, you should do which of the following? 1) Compare the actual quantity used with the direct material that should be used for the actual output. 2) Subtract the budgeted price from the actual price and multiply by the budgeted quantity of materials. 3) Compare the actual amount spent on direct materials with the direct materials shown on the master budget 4) Compare the standard price with the actual price...
The sales-mix variance will be unfavorable when which of the following occurs? A) the actual sales mix shifts toward the less profitable units B) the contribution margin per composite unit for the actual mix is greater than the budgeted mix C) the actual unit sales are less than the budgeted unit sales D) the actual contribution margin is less than the static-budget contribution margin
Are my variance calculations correct? Qty Allowed/Unit Qty Used Budgeted Input Price Actual Input Price Standard Cost per Unit Static Budget (280,000 units) Flexible Budget (325,556 units) Quasi-Budget Total Cost DM Price Variance Status Quantity Variance SP*(SQ-AQ) Total DM Variance Acrylic Pile Fabric 0.02381 7,910 $ 35.00 $ 32.42 $0.83 $ 233,324.00 $ 271,285.81 276,850 $ 256,422 $ 20,428 Favorable (37,962) $ (753,679) 10mm Acrylic Eyes 2 661,248 $ 0.19 $ 0.19 $0.38 $ 106,400.00 $ ...
Norwall Company’s
budgeted variable manufacturing overhead cost is $1.95 per
machine-hour and its budgeted fixed manufacturing overhead is
$36,036 per month.
The following
information is available for a recent month:
The denominator activity of 18,480 machine-hours is used to
compute the predetermined overhead rate.
At a denominator activity of 18,480 machine-hours, the company
should produce 6,600 units of product.
The company’s actual operating results were:
Number of units
produced
7,550
Actual
machine-hours
19,630
Actual variable
manufacturing overhead cost
$
41,223...
The difference between the total actual overhead cost incurred during a period and budgeted total factory overhead cost for the actual quantity of the cost driver used to apply overhead is equal to the: Multiple Choice A: Total overhead spending variance. B: Total overhead efficiency variance. C: Factory overhead production-volume variance. D: Total overhead rate variance. E: Total overhead variance.