Question
calculate the
1.percent scedule variance?
2.percent cost variance?
3.total scedule variance?
4. total cost variance?
M uit ve tal Cost Variance (5 points)? Planned Budget Cost/Time review as of Day 55 Planned Actual Percent Percent Duration D
Planned Budget Cost/Time review as of Day 55 Planned Actual Percent Percent Duration Duration Scheduled Performed Budgeted Co
0 0
Add a comment Improve this question Transcribed image text
Answer #1

We will first calculate budgeted cost of work scheduled and budgeted cost of work performed as shown below:

B E H K L M N A Planned Budget Planned Planned Duration planned Actual Duration Actual Percent Scheduled Percent Percent Perf

Planned Value is the approved value of the work to be completed in a given time.

PV= $2,686

Actual Cost is the total expense incurred for the actual work completed to date ( Day 55),

AC = $2,310

Earned Value is the work actually completed to date (Day 55),

EV = $2,130

3. Total schedule variance, SV = EV – PV

SV = $2,130 - $2,686

SV= - $556

Project is behind schedule since Schedule Variance is negative.

4. Total cost variance, CV = EV – AC

CV = $2,130 - $2,310

CV = - $180

Project is over budget since Cost Variance is negative.

1. Percent schedule variance, SV % = Schedule Variance (SV) / Planned Value

SV % = - $556/   $2,686

SV % = - 20.70%

2. Percent cost variance, CV % = Cost Variance (CV) / Earned Value

CV% = - $180 / $2,130

CV% = -8.45%

Please give thumbs up/ likes if you find this answer helpful. Thank you!

  

Add a comment
Know the answer?
Add Answer to:
calculate the 1.percent scedule variance? 2.percent cost variance? 3.total scedule variance? 4. total cost variance? M...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For a project, in X day, planned value, earned value and actual cost of the tasks...

    For a project, in X day, planned value, earned value and actual cost of the tasks are given in dollar in the table below. Planned $1000 to complete project. Task Actual Cost Work Performed Budgeted Cost Work Scheduled 50 70 30 100 50 2 3 4 5 Budgeted Cost Work Performed 50 70 30 50 0 Total: 250 a. Find schedule and cost variance. Explain what it means? b. Find schedule and cost performance index. c. Find estimate to complete...

  • RUSTIC CABIN-Cost breakdown for 2,000ft2 cabin. Estimate: $250,000. COST ITEMS PERCENT OF TOTAL COST 1. Construction...

    RUSTIC CABIN-Cost breakdown for 2,000ft2 cabin. Estimate: $250,000. COST ITEMS PERCENT OF TOTAL COST 1. Construction permits, legal, and title fees 8 2. Roadway, site clearing and preparation 15 3. Foundation, concrete and masonry 4. Wallboard, carpentry, and flooring 5. Heating, ventilation, air conditioning (HVAC) 6. Electric, plumbing and communications 7. Roofing and flooring 12 8. Painting and finishing 17 100 What is the price per sq. ft. of the 2,000ft2 cabin? $135 O $100 O $150 O $125

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is...

    Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is 11,945 square feet in size with construction scheduled to commence on January 18, 2017. Use the progress completion schedule from a similar CVS Pharmacy in Athens, OH, to organize the overall schedule for the project by weekly progress for a completion date (turn over to owner) on May 23, 2017. 1. Progress in one week: awnings, landscaping, permanent electrical power, gas service 2. Progress...

  • #1. A project in its 26th week has an actual cost of $270,000. It was scheduled...

    #1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...

  • 1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...

    1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • 1. Variable overhead spending? 2. Variable overhead efficiency variance? 3. Total variable overhead variance? 4. Fixed...

    1. Variable overhead spending? 2. Variable overhead efficiency variance? 3. Total variable overhead variance? 4. Fixed overhead spending variance? 5. Fixed overhead volume variance? 6. Total fixed overhead variance? Montreal Inc. manufactures garden hoses for large stores. The standard costs for a dozen garden hoses are as follows: Direct materials Direct labour 24 m x $2 per metre = $48.00 3.40 hours x $12 per hour = $40.80 During February, Montreal Inc. worked on three separate orders of garden hoses....

  • Analyze the cost data received for the given project activities (provided in table) using earn value...

    Analyze the cost data received for the given project activities (provided in table) using earn value management technique and find the values of below questions; 1. Are we ahead or behind schedule? Find the value of variance in Rupees (Rs.) & in percentage If there is any deviation from work planned. 2. How efficiently are we using time? 3. Are we over or under budget? Express the variance in Rupees (Rs.) & in percentage. 4. How efficiently are we using...

  • can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was...

    can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was an established construction company handling small-to medium- sized commercial and industrial construction projects. Some recent projects that the company had completed were a 20,000-square-foot factory building, a four-story office building, and a water filtration plant. TELEVISION TOWER BID The company was now in the process of preparing a bid for a television station for the erection of a 225-foot-high television antenna tower and the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT