Q.1 Flexible Budget :
XYZ Company
Flexible Manufacturing Overhead Budget Report | ||||||
Variable Overhead | Per Labor Hour | Labor Hours | ||||
16,000 | 18,000 | 20,000 | 22,000 | 24,000 | ||
Indirect Labour | 0.30 | 4,800 | 5,400 | 6,000 | 6,600 | 7,200 |
Indirect Material | 0.20 | 3,200 | 3,600 | 4,000 | 4,400 | 4,800 |
Repairs | 0.15 | 2,400 | 2,700 | 3,000 | 3,300 | 3,600 |
Utilities | 0.11 | 1,760 | 1,980 | 2,200 | 2,420 | 2,640 |
Lubricants | 0.04 | 640 | 720 | 800 | 880 | 960 |
Total Variable Oveheads | 12,800 | 14,400 | 16,000 | 17,600 | 19,200 | |
Fixed Overheads | ||||||
Super Vision | 6,250 | 6,250 | 6,250 | 6,250 | 6,250 | |
Depreciation | 2,500 | 2,500 | 2,500 | 2,500 | 2,500 | |
Insurance | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | |
Rent | 750 | 750 | 750 | 750 | 750 | |
Property Tax | 500 | 500 | 500 | 500 | 500 | |
Total Fixed Overhead | 11,000 | 11,000 | 11,000 | 11,000 | 11,000 | |
Total Variable & Fixed Overhead | 23,800 | 25,400 | 27,000 | 28,600 | 30,200 |
Q.2 January Budget Report :
XYZ company :
January Manufacturing Overhead budget Report | |||
Variable Overhead | Budget | Actual | Variance |
Indirect Labour | 6,000 | 6,300 | (300) |
Indirect Material | 4,000 | 3,800 | 200 |
Repairs | 3,000 | 2,700 | 300 |
Utilities | 2,200 | 1,900 | 300 |
Lubricants | 800 | 830 | (30) |
Total Variable Oveheads | 16,000 | 15,530 | 470 |
Fixed Overheads | |||
Super Vision | 6,250 | 6,250 | - |
Depreciation | 2,500 | 2,500 | - |
Insurance | 1,000 | 1,000 | - |
Rent | 750 | 750 | - |
Property Tax | 500 | 500 | - |
Total Fixed Overhead | 11,000 | 11,000 | - |
Total Variable & Fixed Overhead | 27,000 | 26,530 | 470 |
Project 2: Flexible Budget and Budget Report (10 points) Upload your file to Moodle by the...
upe WZ Company estimates that 240,000 direct labor hours will be worked during 2018 in the Painting Department. Based on this estimate, the following budget was developed for manufacturing overhead costs. Variable Overhead Costs Indirect labor $72,000 Indirect materials 48,000 Repairs 36,000 Utilities 26,400 Lubricants 9,600 $192,000 Fixed Overhead Costs Supervision $75,000 Depreciation 30,000 Insurance 12,000 Rent 9,000 Property taxes 6,000 $132,000 It is estimated that direct labor hours worked each month will range from 16,000 to 24,000 hours. During...
(b) Prepare a flexible budget report for October. (List variable costs before fixed costs.) BUMBLEBEE COMPANY Packaging Department Manufacturing Overhead Flexible Budget Report For the Month Ended October 31, 2020 Difference Favorable Unfavorable Neither Favorable nor Unfavorable Budget Actual Costs Bumblebee Company estimates that 387,400 direct labor hours will be worked during the coming year, 2020, in the Packaging Department. On this basis, the following budgeted manufacturing overhead cost data are computed for the year. Fixed Overhead Costs Variable Overhead...
only a LILLE UUCU LUC Salut IULULL cost per day supporting budgets by quarters. (Note: Use variable and fixed in the selling and adminis- trative expense budget.) Do not prepare the manufacturing overhead budget or the direct materials budget for Dert. 1 Dunes Company estimates that 240,000 direct labor hours will be worked during 2017 in the Assembly Department. On this basis, the following budgeted manufacturing overhead data are computed. Prepare flexible budget and budget report for manufacturing overhe (LO...
(a) Prepare a monthly manufacturing overhead flexible budget for each increment of 2,100 direct labor hours over the relevant range for the year ending December 31, 2020. (List variable costs before fixed costs.) (b) Prepare a flexible budget report for October. (List variable costs before fixed costs.) Marigold Company estimates that 372,900 direct labor hours will be worked during the coming year, 2020, in the Packaging Department. On this basis, the following budgeted manufacturing overhead cost data are computed for...
(a) Prepare a monthly manufacturing overhead flexible budget for each increment of 2,100 direct labor hours over the relevant range for the year ending December 31, 2020. (List variable costs before fixed costs.) b) Prepare a flexible budget report for October. (List variable costs before fixed costs.) ^These three additional entries finish off problem three. Thank you! Problem 23-1A a-b (Video) Marigold Company estimates that 372,900 direct labor hours will be worked during the coming year, 2020, in the Packaging...
Johnson Company estimates that 378,500 direct labor hours will be worked during the coming year, 2020, in the the Packaging Department. On this basis, the following budgeted manufacturing overhead cost data are computed for the year. Fixed Overhead Costs _______________________________ Supervision $87,840 Depreciation $68,760 Insurance $30,000 Rent $24,360 Property Taxes $18,480 Total: $229,440 Variable Overhead Costs __________________________________ Indirect labor $166,540 Indirect materials $83,270 Repairs $37,850 Utilities $75,700 Lubricants $30,280 Total: $393,640 It is estimated that direct labor hours worked each...
& BACK Problem 10-1A a-b (Video) Bumblebee Company estimates that 385,800 direct labor hours will be worked during the coming year, 2020, in the Packaging Department. On this basis, the following budgeted manufacturing overhead cost data are computed for the year. Fixed Overhead Costs Supervision $91,080 Depreciation 74,520 Insurance 24,840 Rent 22,560 Property taxes 17,880 $230,880 Variable Overhead Costs Indirect labor $185,184 Indirect materials 100,308 Repairs 61,728 Utilities 57,870 Lubricants 30,864 435.954 It is estimated that direct labor hours worked...
Bumblebee Company estimates that 379,500 direct labor hours will be worked during the coming year, 2017, in the Packaging Department. On this basis, the budgeted manufacturing overhead cost data are computed for the year. Variable Overhead Costs Fixed Overhead Costs Supervision $94,440 Indirect labor $174,570 Depreciation 73,320 Indirect materials 75,900 25,560 Repairs Insurance 53,130 Rent 21,120 Utilities 94,875 Property taxes 20,880 Lubricants 37,950 $436,425 $235,320 It is estimated that direct labor hours worked each month will range from 24,900 to...
Question 20 -/1 View Policies Current Attempt in Progress Bumblebee Company estimates that 322,300 direct labor hours will be worked during the coming year, 2020, in the Packaging Department. On this basis, the following budgeted manufacturing overhead cost data are computed for the year. Fixed Overhead Costs Variable Overhead Costs $85,680 $128,920 Supervision Indirect labor 74,280 Depreciation Indirect materials 83,798 24,600 Repairs Insurance 45,122 48,345 Utilities Rent 18,120 Property taxes 19,320 Lubricants 16,115 $222,000 $322,300 It is estimated that direct...
Bumblebee Company estimates that 366,700 direct labor hours will be worked during the coming year, 2017, in the Packaging Department. On this basis, the budgeted manufacturing overhead cost data are computed for the year. Fixed Overhead Costs Supervision Depreciation Insurance Rent Property taxes $90,000 75,240 31,320 27,000 13,200 $236,760 Variable Overhead Costs Indirect labor $168,682 Indirect materials 102,676 Repairs 73,340 Utilities 55,005 Lubricants 18,335 $418,038 It is estimated that direct labor hours worked each month will range from 29,200 to...