Question

At some point in the life of a project, the project manager determined the following data...

At some point in the life of a project, the project manager determined the following data on a $1,250,000 authorized budget project: amount of earned value $350,000. At that point, the value of the planned work was $750,000, and actual cost was $750,000.

Using the data provided above, and assuming a linear cost function, the project manager can estimate that actual cost of the project would be closest to (figures rounded to nearest hundred thousand):

  1. $4,500,000
  2. $2,700,000
  3. $2,400,000
  4. $2,100,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost Variance = Actual cost - Planned cost = 750000-750000= 0

Performance Index of project =Earned Value/Planned Value = 350000/750000 = 0.47

actual cost of the project = $1,250,000 / 0.47 = $ 2,659,574

which close to option b:$2,700,000

Add a comment
Know the answer?
Add Answer to:
At some point in the life of a project, the project manager determined the following data...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • At some point in the life of a project, the project manager determined the following data...

    At some point in the life of a project, the project manager determined the following data on a $1,250,000 authorized budget project: amount of earned value $350,000. At that point, the value of the planned work was $750,000, and actual cost was $750,000. Based on this information, the Schedule Performance Index for this project was: 0.28 0.47 0.53 0.60

  • The following table shows the current status data for a project at the end of month...

    The following table shows the current status data for a project at the end of month 3. PV (Planned Value) EV (Earned Value) AC (Actual Cost) SV CV SPI CPI $18,461.54 $35,673.08 $20,673.08 If you were the project manager for this project, should you have any concerns about this data? If yes, then what are your concerns? what might be some underlying causes? how might you combat these in the future? If no, then explain why not.

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • Q4 Maria is a project manager for a company that produces two types of appliances each...

    Q4 Maria is a project manager for a company that produces two types of appliances each year for local suppliers. The project requires 200 appliances to be produced per month for Appliance A with a cost of RM 50 each, and 100 appliances to be produced per month for Appliance B with a cost of RM 100 each. Maria receives a project budget of RM 200,000 for 10 months to produce both appliances. After Maria's project team into six months...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it Page 6 of 8 IS8100-01 Fa2019 under or over budget? Use all of the calculated variances and indexes from above to support your argument. [50-100-word response.]

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT