Question

Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...

Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $224,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $44,900 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $228,000, will have a total useful life of 11 years (including the year just completed), and will produce net annual cash flows of $37,500 per year. Click here to view PV table.

Evaluate the success of the project. Assume a discount rate of 12%. (If the net present value is negative, use either a negative sign preceding the number eg -45 or parentheses eg (45). Round present value answers to 0 decimal places, e.g. 125. For calculation purposes, use 5 decimal places as displayed in the factor table provided.)

Original estimate net present value $

Revised estimate net present value $


The project

isis not

a success.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Computation of Original Estimate NPV
Particulars Period PV Factor Amount Present Value
Cash outflows:
Initial investment 0 1 $224,000 $224,000
Present Value of Cash outflows (A) $224,000
Cash Inflows
Annual cash inflows 1-9 5.32825 $44,900 $239,238
Present Value of Cash Inflows (B) $239,238
Net Present Value (NPV) (B-A) $15,238
Computation of Revised Estimate NPV
Particulars Period PV Factor Amount Present Value
Cash outflows:
Initial investment 0 1 $228,000 $228,000
Present Value of Cash outflows (A) $228,000
Cash Inflows
Annual cash inflows 1-11 5.93770 $37,500 $222,664
Present Value of Cash Inflows (B) $222,664
Net Present Value (NPV) (B-A) -$5,336

As revised estimate NPV is negative, therefore project is not a success.

Add a comment
Know the answer?
Add Answer to:
Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...

    Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $227,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $43,700 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $231,000, will have a total useful life of 11 years (including the year just completed), and...

  • Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...

    Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $244,230, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $46,700 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $228,895, will have a total useful life of 11 years, and will produce net annual cash...

  • Brief Exercise 26-6 Quillen Company is performing a post-audit of a project completed one year ago....

    Brief Exercise 26-6 Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $224,418, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $44,900 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $227,644, will have a total useful life of 11 years, and will produce...

  • Brief Exercise 27-06 Quillen Company is performing a post-audit of a project completed one year ago....

    Brief Exercise 27-06 Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $244,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $46,600 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $256,000, will have a total useful life of 11 years (including the year...

  • your answer is partially correct. Try again. Quillen Company is performing a post-audit of a project completed one...

    your answer is partially correct. Try again. Quillen Company is performing a post-audit of a project completed one year 20. The initial estimates were that the project would cost $249,453 would have a useful life of years, zero salvage value and would result in net annual cash flow of $45.300 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $260.336, will have a total useful life of 11 years,...

  • Partially correct answer. Your answer is partially correct. Try again. Quillen Company is performing a post-audit...

    Partially correct answer. Your answer is partially correct. Try again. Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $255,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $43,000 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $261,000, will have a total useful...

  • McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $592,821,...

    McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $592,821, has an expected useful life of 15 years, a salvage value of zero, and is expected to increase net annual cash flows by $75,000. Project B will cost $396,957, has an expected useful life of 15 years, a salvage value of zero, and is expected to increase net annual cash flows by $51,400. A discount rate of 8% is appropriate for both projects. Click...

  • McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $464,000,...

    McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $464,000, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $68,100. Project B will cost $342,000, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $50,900. A discount rate of 8% is appropriate for both projects. Click...

  • McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $400,000,...

    McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $400,000, has an expected useful life of 10 years, a salvage value of zero, and is expected to increase net annual cash flows by $70,000. Project B will cost $310,000, has an expected useful life of 10 years, a salvage value of zero, and is expected to increase net annual cash flows by $55,000. A discount rate of 9% is appropriate for both projects. Compute...

  • McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $522,828,...

    McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $522,828, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $72,100. Project B will cost $324,141, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $46,400. A discount rate of 7 % is appropriate for both projects....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT