Question

Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...


Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $227,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $43,700 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $231,000, will have a total useful life of 11 years (including the year just completed), and will produce net annual cash flows of $36,300 per year. Click here to view PV table.

Evaluate the success of the project. Assume a discount rate of 11%. (If the net present value is negative, use either a negative sign preceding the number eg -45 or parentheses eg (45). Round present value answers to 0 decimal places, e.g. 125. For calculation purposes, use 5 decimal places as displayed in the factor table provided.)

Original estimate net present value $
Revised estimate net present value $


The project                                                           is is not a success.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per the Case;

Let us evaluate each phase with the present values Annuity of the Cashflows.

So,

Initially the project started with 227,000

Present Values of Annuity @ 11% for 9 years is: 5.5370

Then, PV of Cash Flows=Net Annual Inflow X PV factor

46000X5.5370=254,702

Net Present Value=Present Value of Cashflows-Capital Investment

254,702-227,000=27,702

If the project is revised

Present Value of Annuity will be @11% for 11 is:6.2065

Then, PV of Cash Flows=Net Annual Inflow X PV factor

36,300X6.2065=225,296

Net Present Value=Present Value of Cashflows-Capital Investment

225,296-231,000=(5,704)

Hence, The result shows that initial investment is positive with the amount of 27,702 but the revised project has a negative investment of (5,704). Hence the project is NOT SUCCESSFUL.

Original Estimate Net Present Value: 254,702-227,000=27,702

Revised Estimate Net Present Value: 225,296-231000=(5,704)

Add a comment
Know the answer?
Add Answer to:
Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...

    Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $224,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $44,900 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $228,000, will have a total useful life of 11 years (including the year just completed), and...

  • Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates...

    Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $244,230, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $46,700 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $228,895, will have a total useful life of 11 years, and will produce net annual cash...

  • Brief Exercise 27-06 Quillen Company is performing a post-audit of a project completed one year ago....

    Brief Exercise 27-06 Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $244,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $46,600 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $256,000, will have a total useful life of 11 years (including the year...

  • Brief Exercise 26-6 Quillen Company is performing a post-audit of a project completed one year ago....

    Brief Exercise 26-6 Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $224,418, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $44,900 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $227,644, will have a total useful life of 11 years, and will produce...

  • your answer is partially correct. Try again. Quillen Company is performing a post-audit of a project completed one...

    your answer is partially correct. Try again. Quillen Company is performing a post-audit of a project completed one year 20. The initial estimates were that the project would cost $249,453 would have a useful life of years, zero salvage value and would result in net annual cash flow of $45.300 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $260.336, will have a total useful life of 11 years,...

  • Partially correct answer. Your answer is partially correct. Try again. Quillen Company is performing a post-audit...

    Partially correct answer. Your answer is partially correct. Try again. Quillen Company is performing a post-audit of a project completed one year ago. The initial estimates were that the project would cost $255,000, would have a useful life of 9 years, zero salvage value, and would result in net annual cash flows of $43,000 per year. Now that the investment has been in operation for 1 year, revised figures indicate that it actually cost $261,000, will have a total useful...

  • Brief Exercise 26-5 McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A...

    Brief Exercise 26-5 McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $450,241, has an expected useful life of 11 years, a salvage value of zero, and is expected to increase net annual cash flows by $73,500. Project B will cost $298,321, has an expected useful life of 11 years, a salvage value of zero, and is expected to increase net annual cash flows by $50,200. A discount rate of 9% is appropriate for...

  • Coronado Company is considering a long-term investment project called ZIP. ZIP will require an investment of...

    Coronado Company is considering a long-term investment project called ZIP. ZIP will require an investment of $122,200. It will have a useful life of 4 years and no salvage value. Annual cash inflows would increase by $79,800, and annual cash outflows would increase by $39,900. The company’s required rate of return is 11%. Click here to view PV table. Calculate the net present value on this project. (If the net present value is negative, use either a negative sign preceding...

  • McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $592,821,...

    McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $592,821, has an expected useful life of 15 years, a salvage value of zero, and is expected to increase net annual cash flows by $75,000. Project B will cost $396,957, has an expected useful life of 15 years, a salvage value of zero, and is expected to increase net annual cash flows by $51,400. A discount rate of 8% is appropriate for both projects. Click...

  • McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $464,000,...

    McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $464,000, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $68,100. Project B will cost $342,000, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $50,900. A discount rate of 8% is appropriate for both projects. Click...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT