Question

12. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the...

12. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the same appropriate discount rate. Project Alpha generates infinite after tax cash flows which do not grow; the first cash flow is $80M one year from now (T=1) and will cost $600M today (T=0). Project Beta generates infinite after tax cash flows which do not grow; the first cash flow is $40M one year from now (T=1) and will cost $300M today (T=0). Which statement about the crossover rate for Project Alpha and Project Beta is most accurate?

  1. If the appropriate discount rate for both projects was below the crossover rate of 13.3%, Project Alpha would have a better NPV than Project Beta

  2. If the appropriate discount rate for both projects was below the crossover rate of 4.4%, Project Alpha would have a better NPV than Project Beta

  3. If the appropriate discount rate for both projects was above the crossover rate of 4.4%, Project Alpha would have a better NPV than Project Beta

  4. If the appropriate discount rate for both projects was above the crossover rate of 13.3%, Project Alpha would have a better NPV than Project Beta

  5. If the appropriate discount rate for both projects was below the crossover rate of 20.0%, Project Alpha would have a better NPV than Project Beta

0 0
Add a comment Improve this question Transcribed image text
Answer #1

project Beta

Project Alpha

incremental cash flow

cash outflow

-300

-600

-300

cash inflow

40

80

40

cross over rate = cash inflow/cash outflow

40/300

13.33%

NPV of project Alpha

cash outflow

-600

cash inflow

80

present value of cash inflow = cash inflow/cross over rate

80/13.33%

600.15004

NPV of project Alpha

600.15-600

0.15

NPV of project Beta

cash outflow

-300

cash inflow

40

present value of cash inflow = cash inflow/cross over rate

40/13.33%

300.07502

NPV of project Alpha

300.075-300

0.075

If the appropriate discount rate for both projects was below the crossover rate of 13.3%, Project Alpha would have a better NPV than Project Beta

Add a comment
Know the answer?
Add Answer to:
12. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1 2. Assume you are trying to compare Project Alpha to Project Beta. Both projects have...

    1 2. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the same appropriate discount rate. Project Alpha generates infinite after tax cash flows which do not grow; the first cash flow is $80M one year from now (T=1) and will cost $600M today (T=0). Project Beta generates infinite after tax cash flows which do not grow; the first cash flow is $40M one year from now (T1) and will cost $300M today (T 0)....

  • 2. Assume you are tr compare Project Alpho to Project Beta. Both projects hove the some...

    2. Assume you are tr compare Project Alpho to Project Beta. Both projects hove the some discount rote. Project Alpha generates infinike after tox cash flows which dlo not grow the 0M one year from no (T 1) ond wil cost $600M today (T-o). Project Beta first cash flow is $8 Penerates infinite ofter tax cash flows which do not grow; the first cosh flow is $40M one year from now t about the crossover rate for Project Alpho and...

  • 2. Assume you are tr compare Project Alpho to Project Beta. Both projects hove the some...

    2. Assume you are tr compare Project Alpho to Project Beta. Both projects hove the some discount rote. Project Alpha generates infinike after tox cash flows which dlo not grow the 0M one year from no (T 1) ond wil cost $600M today (T-o). Project Beta first cash flow is $8 Penerates infinite ofter tax cash flows which do not grow; the first cosh flow is $40M one year from now t about the crossover rate for Project Alpho and...

  • 12. Asume you ore trying to compore Project Alphe no Project Beto. Both peojecs hove the...

    12. Asume you ore trying to compore Project Alphe no Project Beto. Both peojecs hove the some appropriate discount rate. Projedt Alpha generates infinite aher tax cosh flows which do not grow the first cosh flow is $8OM one yeor from now (T 1) ando $600M today (T-O, Project Beto generones infinite after tax eash flows which do not grow the fist cosh Flow is $40M one year from now Project Beta is most acurate o. "" e appropriate discount...

  • 1. Calculate the net present value (NPV) for both projects, and determine which project should be...

    1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. 2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR. 3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar. Please show all work. Thank you. Use...

  • Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000,...

    Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years, and an IRR of 16.63%. The projects are equally risky. Which of the following statements is CORRECT? Since the smaller project has the higher IRR, the two projects’ NPV profiles will cross, and the...

  • You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project...

    You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -28 -43 1 30 45 2 40 50 Part 1 What is the crossover rate, i.e., the discount rate at which both projects have the same NPV?

  • No need for Explanation The CFO of a major corporation is trying to decide on what...

    No need for Explanation The CFO of a major corporation is trying to decide on what project to pursue using different investment criteria: Net Present Value (NPV), Payback Period, Discounted Payback Period, Internal Rate of Return (IRR), and the Profitability Index (PI). The CFO has four projects to choose between: Project W (which is a strip mine - see problem 6), Project X, Project Y, and Project Z. Additional information about each project is summarized below. You can use the...

  • Canfly Airlines is considering two mutually exclusive projects, Project A and Project B. The projects have...

    Canfly Airlines is considering two mutually exclusive projects, Project A and Project B. The projects have the following cash flows (in millions of dollars): Year Project A Cash Flow Project B Cash Flow 0 -$4.0 -$4.5 1 2.0 1.7 2 3.0 3.2 3 5.0 ? The crossover rate of the two projects’ NPV profiles is 9 percent. What is the cash flow for Project B at t = 3? (Ans: 5.79 million)

  • The CFO of a major corporation is trying to decide on what project to pursue using...

    The CFO of a major corporation is trying to decide on what project to pursue using different investment criteria: Net Present Value (NPV), Payback Period, Discounted Payback Period, Internal Rate of Return (IRR), and the Profitability Index (PI). The CFO has four projects to choose between: Project W (which is a strip mine - see problem 6), Project X, Project Y, and Project Z. Additional information about each project is summarized below You can use the workspace provided to help...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT