Part 1
Strength-testing one item from each batch of panels |
Appraisal |
Training employees in TQM |
Prevention |
Training suppliers in TQM |
Prevention |
Identifying suppliers who commit to on-time delivery of perfect-quality materials |
Prevention |
Avoid lost profits from lost sales due to disappointed customers |
External Failure |
Avoid rework and spoilage |
Internal Failure |
Avoid inspection of raw materials |
Appraisal |
Avoid warranty costs |
External Failure |
Part 2
Christianson should implement the new TQM program. The program would save the company $53,000
Because the total cost of undertaking the new TQM program ($172,000) is less than the total cost of not undertaking the new TQM program ($225,000) by $53,000.
Undertake the New TQM Program
Prevention |
|
Training employees in TQM |
21000 |
Training suppliers in TQM |
37000 |
Identifying suppliers who commit to on-time delivery of perfect-quality materials |
54000 |
Total prevention costs |
112000 |
Appraisal |
|
Strength-testing one item from each batch of panels |
60000 |
Total appraisal costs |
60000 |
Total costs of undertaking the new TQM program |
$172000 |
Do Not Undertake the New TQM Program
Appraisal |
|
Avoid inspection of raw materials |
56000 |
Total appraisal costs |
56000 |
Internal Failure |
|
Avoid rework and spoilage |
67000 |
Total internal failure costs |
67000 |
External Failure |
|
Avoid lost profits from lost sales due to disappointed customers |
95000 |
Avoid warranty costs |
17000 |
Total external failure costs |
102000 |
Total costs of not undertaking the new TQM program |
$225000 |
Christianson Corp. manufactures radiation-shielding glass panels. (Click the icon to view the information.) Click the con...
ClasonClason Corp. manufactures radiation-shielding glass panels. LOADING... (Click the icon to view the information.) Requirements 1. Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost. 2. Should ClasonClason implement the new quality program? Give your reason. Requirement 1. Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost. Type of Quality Cost Cost Strength-testing one item from each batch of panels...
Clason, Inc. manufactures door panels. Suppose Clason is considering spending the following amounts on a new total quality management (TQM) program (Click the icon to view the information. Clason expects the new program would save costs through the following: (Click the icon to view the information.) Read the requirements. e cost or Requirement 1. Classify each cost as a prevention cost, an appraisal cost, an internal failu an external failure cost. Cost Type of Quality Cost Strength-testing one item from...
Learning Objective 52 Classifying quality costs and using these costs to make decisions Loiselle manufactures high-quality speakers. Suppose Loiselle is considering spending he following amounts on a new quality program: 2. Total cost to underta $2,305,000 $ 625,000 Additional 20 minutes testing for each speaker Negotiating and training suppliers to obtain higher-quality materials and on-time delivery Redesigning the speakers to make them easier to manufacture 430,000 1,250,000 Loiselle expects this quality program to save costs as follows: Reduce warranty repair...
Click the Requiremec 1. Classify 2. Should Le Data Table malt Requireme external fail hal far Larter is considering spending the following amounts on the new program Additional 20 minutes testing for each speaker $ 620.000 Negotiating and training suppliers to obtain higher quality materials and on time delivery 350.000 Redesigning the speakers to make them easier to manufacture 1.450.000 Additional 2 Larter expects this quality program to save costs as follows Reduce warranty repair costs 250,000 Avoid inspection of...
Homework: Ch 4 HW Score: 0 of 1 pt S4-16 (similar to) 8 of 8 (5 complete) HW Score: 48.72%, 3. Question H Terrordomo manufactures high-quality speakers. Suppose Terrordome is considering spending the following amounts on a new quality program: (Click the icon to view the information.) Terrordome expects this quality program to save costs as follows: FF (Click the icon to view the information) It also expects this program to avoid lost profits from the following: (Click the icon...
The following represents the financial information for Domingo Corporation for two months. March April $360,000 Sales revenue $540,000 Costs $ 1,550 1,820 Process inspection 1,940 1,870 13,300 Scrap Quality training Warranty repairs Product testing equipment Customer complaints 20,600 4,300 6,700 2,500 16,000 15,100 6,400 9,800 4,800 7,500 3,100 20,000 9,400 4,700 Rework Preventive maintenance Materials inspection Field testing 13,500 Required: a. Classify these items into Prevention, Appraisal, Internal failure, or External failure costs. b. Calculate the ratio of the prevention,...
Listed below are eight components of the total cost of quality. In the spaceprovided identify each as a cost of prevention, appraisal, internal failure, or extemal failure 1. Product design 2. Product returns due to defects 3. Inspection of raw materials shipments 4. Employee training 5. Rework of defective units prior to shipment 6. Estimated lost sales due to poor quality 7. Warranty expense 8. Inspection of finished goods 9. Scrap
Required A Required B Calculate the ratio of the prevention, appraisal, internal failure, and external failure costs to sales for March and April. (Enter your answers as a percentage rounded to 1 decimal place (i.e., 32.1).) March April Prevention Appraisal Internal failure External failure % % % % % % % % The following represents the financial information for Domingo Corporation for two months. March $515,000 April $440,000 Sales revenue Costs Process inspection Scrap Quality training Warranty repairs Product testing...
The following represents the financial information for Domingo Corporation for two months. March April Sales revenue $ 540,000 $ 440,000 Costs Process inspection $ 1,800 $ 1,890 Scrap 1,840 1,860 Quality training 20,700 13,400 Warranty repairs 4,300 4,700 Product testing equipment 7,300 6,700 Customer complaints 3,000 3,500 Rework 17,000 19,000 Preventive maintenance 11,800 9,300 Materials inspection 5,900 5,200 Field testing 10,000 13,800 Required: a. Classify these items into Prevention, Appraisal, Internal failure, or External failure costs. b. Calculate the ratio...
The following represents the financial information for Domingo Corporation for two months. March $498,000 April $456,000 $ $ Sales revenue Costs Process inspection Scrap Quality training Warranty repairs Product testing equipment Customer complaints Rework Preventive maintenance Materials inspection Field testing 3,050 2,200 21,200 6,400 7,700 3,850 17,700 14,900 7,900 10,800 3,280 2,280 14,400 6,900 7,700 4,450 22,000 10,900 6,200 13,800 Required: Construct a cost of quality report for March and April. (Input all amounts as positive values. Round percentage answers...