Cost |
Type of quality cost |
Additional 20 minutes of testing for each speaker |
Appraisal |
Negotiating with and training suppliers to obtain higher quality materials and on-time delivery |
Prevention |
Redesigning the speakers to make them easier to manufacture |
Prevention |
Reduced warranty repair costs |
External failure |
Avoid inspection of raw materials |
Appraisal |
Avoid rework because of fewer defective units |
Internal failure |
Lost sales due to disappointed customers |
External failure |
Lost production time due to rework |
Internal failure |
Part 2
Costs of Implementing New Quality Program: |
|
Prevention costs: |
|
Negotiating with and training suppliers to obtain higher quality materials and on-time delivery |
350000 |
Redesigning the speakers to make them easier to manufacture |
1450000 |
Appraisal costs: |
|
Additional 20 minutes of testing for each speaker |
620000 |
Total costs of implementing the new quality program |
$2420000 |
Costs of Not Implementing New Quality Program: |
|
Appraisal costs: |
|
Inspection of raw materials |
490000 |
Internal failure costs: |
|
Rework |
810000 |
Lost profits from lost production time due to rework |
276000 |
External failure costs: |
|
Warranty repair costs |
250000 |
Lost profits from lost sales due to disappointed customers |
890000 |
Total costs of not implementing new quality program |
$2716000 |
Larter should implement the new quality program. The cost of implementing the program ($2420000) is $296,000 less than the costs of failing to implement the program ($2716000)
Click the Requiremec 1. Classify 2. Should Le Data Table malt Requireme external fail hal far...
Homework: Ch 4 HW Score: 0 of 1 pt S4-16 (similar to) 8 of 8 (5 complete) HW Score: 48.72%, 3. Question H Terrordomo manufactures high-quality speakers. Suppose Terrordome is considering spending the following amounts on a new quality program: (Click the icon to view the information.) Terrordome expects this quality program to save costs as follows: FF (Click the icon to view the information) It also expects this program to avoid lost profits from the following: (Click the icon...
Learning Objective 52 Classifying quality costs and using these costs to make decisions Loiselle manufactures high-quality speakers. Suppose Loiselle is considering spending he following amounts on a new quality program: 2. Total cost to underta $2,305,000 $ 625,000 Additional 20 minutes testing for each speaker Negotiating and training suppliers to obtain higher-quality materials and on-time delivery Redesigning the speakers to make them easier to manufacture 430,000 1,250,000 Loiselle expects this quality program to save costs as follows: Reduce warranty repair...
Christianson Corp. manufactures radiation-shielding glass panels. (Click the icon to view the information.) Click the con Requirements 1. Classify each item as a prevention cost, an appraisal cost an internal failure cost, or an external failure cost. 2. Should Christianson implement the new quality program? Give your reason internal fallure cost, Requirement 1. Classify each item as a prevention cost, an appraisal cost, an internal failure cost or an external failure cost Type of Quality Cost Strength testing one item...
ClasonClason Corp. manufactures radiation-shielding glass panels. LOADING... (Click the icon to view the information.) Requirements 1. Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost. 2. Should ClasonClason implement the new quality program? Give your reason. Requirement 1. Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost. Type of Quality Cost Cost Strength-testing one item from each batch of panels...
Clason, Inc. manufactures door panels. Suppose Clason is considering spending the following amounts on a new total quality management (TQM) program (Click the icon to view the information. Clason expects the new program would save costs through the following: (Click the icon to view the information.) Read the requirements. e cost or Requirement 1. Classify each cost as a prevention cost, an appraisal cost, an internal failu an external failure cost. Cost Type of Quality Cost Strength-testing one item from...
Data Table PEL U LIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A ..... $ A Number of units manufactured and sold ....... .......... 2,500 units Selling price per unit .... 2,000 Variable manufacturing and selling costs per unit 1,100 Hours spent by engineers...
1. A number of activities that are a part of a company's quality control system are listed below. Classify the costs associated with each of these activities into one of the following categories: prevention cost, appraisal cost, internal failure cost, or external failure cost. Activities Cost a. Product testing. b. Product recalls c. Rework labor and overhead. d. Quality circles e. Downtime caused by defects f. Cost of field servicing 0 Inspection of goods h. Quality engineering Warranty repairs Statistical...
Grayson Industries manufactures freezers. Here is some information about its "LX17" line of freezers over the past year: (Click the icon to view the information.) Read the requirements Requirement 1. Prepare a Cost of Quality (COD) report. In addition to calculating the total costs of each category, calculate the percentage of COQ category of the total COQ (Round is not used in the table leave the box empty, do not select a label or enter a zero) . Grayson Cost...
Gamma Industries manufactures freezers. Here is some information about its "LX17" line of freezers over the past year: E: (Click the icon to view the information Х Read the requirements Data Table þory of the total COQ. (Round the percentage to the one tenth of a percent, X.X%. If a box is not used in Requirement 1. Prepare a Cost of Qual the table leave the box empty, do not se Number of units manufactured and sold 4,000 units Gamma...
I'm struggling with filling in the boxes below. Help would be much appreciated. 0 Data Table 4,000 units 1,250 650 Number of units manufactured and sold Selling price per unit Variable manufacturing and selling costs per unit Hours spent by engineers improving design ... ................. Testing and inspection hours per unit Percentage of units reworked in the plant after inspection Average variable rework costs per refrigerator Percentage of units repaired under warranty at customers' homes Average variable repair costs at...