Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost
Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected:
Month | Labor Cost | Employee Hours | ||
January | $7,100 | 360 | ||
February | 8,140 | 550 | ||
March | 9,899 | 630 | ||
April | 9,787 | 600 | ||
May | 8,490 | 480 | ||
June | 7,450 | 350 | ||
July | 9,490 | 570 | ||
August | 7,531 | 310 |
Coefficients shown by a regression program for Pizza Vesuvio's data are:
Intercept | 4,562 |
X Variable | 8.15 |
In your calculations, round the variable rate per employee hour to the nearest cent.
Required:
Use the results of regression to make the following calculations:
1. Calculate the fixed cost of labor.
$
Calculate the variable rate per employee hour.
$per employee hour
2. Construct the cost formula for total labor
cost.
Total labor cost = $ + ($ × Employee hours)
3. Calculate the budgeted cost for next month,
assuming that 655 employee hours are budgeted. Round answer to the
nearest dollar.
$
Please show work
Fixed cost of labor = Intercept | ||
Variable rate per employee hour = X Variable | ||
1 | ||
Fixed cost of labor | 4562 | |
Variable rate | 8.15 | per employee hour |
2 | ||
Total labor cost = $4562 + ($8.15 × Employee hours) | ||
3 | ||
Budgeted cost | 9900 | =4562+(655*8.15) |
Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine...
Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $6,900 360 February 8,140 550 March 9,899 630 April 9,787 610 May 8,490 480 June 7,450 350 July 9,490 570 August 7,531 310 Coefficients shown by a regression program for Pizza Vesuvio's data are: Intercept 4,452 X Variable 8.31 In your calculations, round...
Show Me How eBook Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were colle Month Calculator Labor Cost Employee Hours 360 550 630 610 480 350 570 310 $7,000 February March April May une 8,140 9,899 9,787 8,490 7,450 9,490 7,531 August Coefficients shown by a regression program for Pizza Vesuvio's data are: 4,517 X Variable 8.20 In your...
COLOR Video Calculator Print Item Using Regression to Calculate Fixed Cost Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Pizza Vesuvio makes specialty pizzas. Data for the past eight months were collected: Month Labor Cost Employee Hours January $7,000 360 February 8,140 550 March 9,899 630 April 610 9,787 8.490 May 480 June 350 July 9.490 57 August 7,531 Coefficients shown by a regression program for Pizza Vesuvio's data are: Intercept 4,517 X Variable 8.20 Required:...
Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 510 February 7,000 590 March 7,531 620 April 8,140 470 May 9,787 550 June 8,490 430 July 12,708 700 August 7,500 390 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...
Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 380 February 7,000 440 March 7,531 460 April 8,140 350 May 9,787 410 June 8,490 320 July 11,042 ...
Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month January February March Labor Cost($) Employee Hours 9,490 7,000 7,531 8,140 9,787 8,490 April May June July 13,416 7,500 August Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant In your calculations, round the variable rate per employee hour to the nearest...
Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 570 February 7,000 660 March 7,531 700 April 8,140 May 9,787 620 480 June 8,490 July 13,520 790 August 7,500 440 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the variable...
#1 #2 #3 Please show work Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 290 9,490 7,000 February 330 March 7,531 April 8,140 May 9,787 310 240 June 8,490 July 10,776 400 August 7,500 220 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In...
Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $7,000 430 February $9,899 620 March $8,140 700 April $9,787 680 May $8,490 550 June $7,531 420 July $9,490 640 August $7,450 380 Assume that this information was used to construct the following formula for monthly labor cost. Total Labor Cost = $6629+ ($2.16 x Employee Hours)...
Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for a Time Period that Differs from the Data Period Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $7,000 360 February 8,140 550 March 9,899 630 April 9,787 610 May 8,490 480 June 7,450 350 July 9,490 570 August 7,531 310 Assume that this information was used to construct the following formula for monthly labor cost. Total Labor...