Question

Situation I On January 1, 2020, Kingbird, Inc. signed a fixed-price contract to have Builder Associates...

Situation I

On January 1, 2020, Kingbird, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,471,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2020, to finance the construction cost, Kingbird borrowed $4,471,000 payable in 10 annual installments of $447,100, plus interest at the rate of 10%. During 2020, Kingbird made deposit and progress payments totaling $1,676,625 under the contract; the weighted-average amount of accumulated expenditures was $894,200 for the year. The excess borrowed funds were invested in short-term securities, from which Kingbird realized investment income of $265,300.

What amount should Kingbird report as capitalized interest at December 31, 2020?

Capitalized interest

$

Situation II

During 2020, Oriole Corporation constructed and manufactured certain assets and incurred the following interest costs in connection with those activities.

Interest Costs Incurred

Warehouse constructed for Oriole’s own use $33,290
Special-order machine for sale to unrelated customer, produced according
to customer’s specifications
9,660
Inventories routinely manufactured, produced on a repetitive basis 8,250


All of these assets required an extended period of time for completion.

Assuming the effect of interest capitalization is material, what is the total amount of interest costs to be capitalized?

The total amount of interest costs to be capitalized

$

Situation III

Waterway, Inc. has a fiscal year ending April 30. On May 1, 2020, Waterway borrowed $10,886,000 at 11% to finance construction of its own building. Repayments of the loan are to commence the month following completion of the building. During the year ended April 30, 2021, expenditures for the partially completed structure totaled $7,620,200. These expenditures were incurred evenly throughout the year. Interest earned on the unexpended portion of the loan amounted to $707,590 for the year.

How much should be shown as capitalized interest on Waterway’s financial statements at April 30, 2021?

Capitalized interest on Waterway’s financial statements

$

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Anseocen Staalion Capitalized nbe acevmulated 94200 asaighted avge cxpenses Trbeneorabe accomuateo Copitaigedl fntret ightedmatudadun ing oventony not caphaliged Iatenest Sitaation Capitaliged nterer oD oal ercoayancial statement AMAA accumuldted ex

Add a comment
Know the answer?
Add Answer to:
Situation I On January 1, 2020, Kingbird, Inc. signed a fixed-price contract to have Builder Associates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Situation On January 1, 2020, Crane, Inc. signed a fixed-price contract to have Builder Associates construct...

    Situation On January 1, 2020, Crane, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,160,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2020, to finance the construction cost, Crane borrowed $4,160,000 payable in 10 annual installments of $416,000, plus interest at the rate of 10%. During 2020, Crane made deposit and progress payments totaling $1,560,000 under the contract; the weighted...

  • Situation I On January 1, 2017, Tamarisk, Inc. signed a fixed-price contract to have Builder Associates...

    Situation I On January 1, 2017, Tamarisk, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2017, to finance the construction cost, Tamansk borrowed $4,215 000 Payable in 10 annual installments of $421 500 plus interest at the rate of 10% During 2017 Tamarisk made deposit and progress Payments totaling S1 580,625 under...

  • Situation I On January 1, 2017, Tamarisk, Inc signed a fixed-price contract to have Builder Associates...

    Situation I On January 1, 2017, Tamarisk, Inc signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project, Also on January 1, 2017, to finance the construction cost Tamarisk borrowed $4,215,000 payable in 10 annual stallments of $421,500, plus interest at the rate of 10%. Dunng 2017 Tar ansk made deposit and progress payments totaling $1,580,625 under the contract;...

  • The following three situations involve the capitalization of interest. Situation I On January 1, 2017, Temarisk,...

    The following three situations involve the capitalization of interest. Situation I On January 1, 2017, Temarisk, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2017, to finance the construction cost, Tamar k borrowed $4,215,000 payable in 10 annual stal mets of $421,500, plus interest at the rate of 10%. During 2017, Tamarisk...

  • The following three situations involve the capitalization of interest. Situation I On January 1, 2017, Riverbed,...

    The following three situations involve the capitalization of interest. Situation I On January 1, 2017, Riverbed, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,491,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2017, to finance the construction cost, Riverbed borrowed $4,491,000 payable in 10 annual installments of $449,100, plus interest at the rate of 10% During 2017, Riverbed made deposit...

  • Exercise 10-10 The following three situations involve the capitalization of interest. Situation I major plant facility...

    Exercise 10-10 The following three situations involve the capitalization of interest. Situation I major plant facility at a cost of $4,419,000. It was esti mated that it On January 1, 2017, Martinez, Inc. signed a fixed-price contract to have Builder Associates construct would take 3 years to complete the project. Also on January 1, 2017, to finance the construction cost, Martinez borrowed $4,419,000 payable in 10 annual installments of $441,900, plus interest at the rate of 10%. During 2017, Martinez...

  • Herr Inc. Has a fiscal year ending April 30. On May 1, of the previous year,...

    Herr Inc. Has a fiscal year ending April 30. On May 1, of the previous year, Herr borrowed $10,000,000 al 15% to finance construction of its own building. Repayments of the loan are to commence the month following completion of the building. During the current year ended April 30, expenditures for the partially completed structure totaled $ 6,000,000. These expenditures were incurred evenly throughout the year. Interest earned on the unexpended portion of the loan amounted to $ 400,000 for...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • Kingbird Inc. is a book distributor that had been operating in its original facility since 1987....

    Kingbird Inc. is a book distributor that had been operating in its original facility since 1987. The increase in certification programs and continuing education requirements in several professions has contributed to an annual growth rate of 15% for Kingbird since 2012. Kingbird, original facility became obsolete by early 2017 because of the increased sales volume and the fact that Kingbird now carries CDs in addition to books. On June 1, 2017, Kingbird contracted with Black Construction to have a new...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT