Problem 3-36A
Agassi Company uses a job order cost system in each of its three
manufacturing departments. Manufacturing overhead is applied to
jobs on the basis of direct labour cost in Department D, direct
labour hours in Department E, and machine hours in Department
K.
In establishing the predetermined overhead rates for 2016, the
following estimates were made for the year.
Department |
||||||
D |
E |
K |
||||
Manufacturing overhead | $1,400,000 | $1,250,000 | $720,000 | |||
Direct labour costs | $2,000,000 | $1,250,000 | $450,000 | |||
Direct labour hours | 100,000 | 125,000 | 40,000 | |||
Machine hours | 400,000 | 500,000 | 120,000 |
During January, the job cost sheets showed the following costs and
production data.
Department |
||||||
D |
E |
K |
||||
Direct materials used | $140,000 | $126,000 | $78,000 | |||
Direct labour costs | $120,000 | $110,000 | $37,500 | |||
Manufacturing overhead incurred | $99,000 | $100,000 | $79,000 | |||
Direct labour hours | 8,000 | 11,000 | 3,500 | |||
Machine hours | 34,000 | 45,000 |
10,300 |
Question: Fill in the blanks
Thank you so much!
Problem 3-36A Agassi Company uses a job order cost system in each of its three manufacturing...
Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,260,000 $1,800,000 100,000 400,000 $1,750,000 $1,250,000 125,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments, Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $990,000 $1,237,500 150,000 600,000 $1,750,000 $1,875,000 125,000 750,000 $1,080,000 $675,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $1,260,000 $1,625,000 $960,000 Direct labor costs $1,800,000 $1,375,000 $495,000 Direct labor hours 110,000 125,000 44,000...
Vaughn Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours D $ 959,000 $ 1,370,000 100,000 400,000 $1,500,000 $1,250,000 125,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $1,080,000 $1,500,000 $1,020,000 Direct labor costs $1,542,857 $1,250,000 $450,000 Direct labor hours 100,000 125,000 40,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 Direct labor costs $1,250,000 $450,000 $959,000 $1,370,000 100,000 400,000 Direct labor hours 125,000 40,000 Machine...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year, Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours 51,800,000 1,500,000 840,000 $2,250,000 1,500,000 540,000 48,000 120,000 120,000 480,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D. direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D. Manufacturing overhead $784,000 $1,500,000 $780,000 Direct labor costs $1,120,000 100,000 $1,250,000 $450,000 Direct labor hours 125,000 40,000 Machine hours...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K In establishing the predetermined overhead rates for 2017, the following estimates were made for the year Manufacturing overhead Direct labor costs Direct labor houns Machine hours $1,800,000 1,500,000 840,000 S2,250,000 1,500,000 $540,000 48,000 120,000 120,000 125,000 480,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. D Manufacturing overhead Direct labor costs Direct labor hours $1,240,000 $1,550,000 120,000 480,000 Department E $1,625,000 $1,500,000 125,000 600,000 K $1,020,000...