Solutions:
Computation of Predetermined overhead rate for Each department | |||
Particulars | D | E | K |
Budgeted Manufacturing Overhead | $12,60,000 | $17,50,000 | $8,40,000 |
/Budgeted direct labor Cost | $18,00,000 | ||
/Budgeted direct labor Hours | 125000 | ||
/Budgeted Machine hours | 120000 | ||
Overhead rate of department | 70% | $14.00 | $7.00 |
Computation of Total manufacturing Cost assigned | |||
Particulars | D | E | K |
Actual Direct labor Cost | $1,20,000 | ||
Actual Direct labor Hours | 11000 | ||
Actual Machine hours | 10310 | ||
Overhead rate of department | 70% | $14.00 | $7.00 |
Manufacturing overhead applied | $84,000 | $1,54,000 | $72,170 |
Add: Direct materials | $1,40,000 | $1,26,000 | $78,000 |
Add: Direct labor | $1,20,000 | $1,10,000 | $37,500 |
Total manufacturing Cost assigned | $3,44,000 | $3,90,000 | $1,87,670 |
Computation of Under/Over applied Overhead | |||
Particulars | D | E | K |
Manufacturing overhead applied | $84,000 | $1,54,000 | $72,170 |
Actual Overhead incurred | $99,000 | $1,24,000 | $79,000 |
Differnce overhead | $15,000 | $30,000 | $6,830 |
Under-applied | Over-applied | Under-applied |
Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three...
Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,260,000 $1,800,000 100,000 400,000 $1,750,000 $1,250,000 125,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments, Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $990,000 $1,237,500 150,000 600,000 $1,750,000 $1,875,000 125,000 750,000 $1,080,000 $675,000...
Problem 2-4A (Video) (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on Ehe basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,170,000 $1,462,500 100,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $1,260,000 $1,625,000 $960,000 Direct labor costs $1,800,000 $1,375,000 $495,000 Direct labor hours 110,000 125,000 44,000...
Problem 2-4A (Video) (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Departme Do Review - Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,170,000 $1,462,500...
please help me get the incorrect 3 Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three manufacturing departments. Mar and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for Department D E K Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,400,000 $2,000,000 100,000 400,000 $1,250,000 $1,250,000 125,000 500,000 $720,000 $450,000 40,000 120,000 During January, the job cost sheets showed the...
Problem 3-36A Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labour cost in Department D, direct labour hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2016, the following estimates were made for the year. Department D E K Manufacturing overhead $1,400,000 $1,250,000 $720,000 Direct labour costs $2,000,000 $1,250,000 $450,000 Direct labour hours 100,000...
RESOURCES oters 14,1. | Problem 2-4A (Video) (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. -4 (Part Level In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department -12 (Video) Submission) -6 (Video) Submission) -4A...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,179,000 $1,684,286 150,000 600,000 $1,750,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. D Manufacturing overhead Direct labor costs Direct labor hours $1,240,000 $1,550,000 120,000 480,000 Department E $1,625,000 $1,500,000 125,000 600,000 K $1,020,000...