Compute the total manufacturing costs assigned to jobs in January in each department:
Answer :
Department |
||||||||
Manufacturing Costs |
D |
E |
K |
|||||
Direct materials Direct labor Overhead applied Total |
$140,000 120,000 84,000 $344,000 |
# |
$126,000 110,000 110,000 $346,000 |
## |
$ 78,000 37,500 61,800 $177,300 |
### |
#$120,000 (direct labor cost) * 70% ( calculated in part 1 )
##11,000 (direct labor hours) X $10.00
###10,300 (machine hours) X $6.00
please help me get the incorrect 3 Problem 2-4A (Video) Agassi Company uses a job order...
Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,260,000 $1,800,000 100,000 400,000 $1,750,000 $1,250,000 125,000...
Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,260,000 $1,800,000 100,000 400,000 $1,750,000 $1,250,000 125,000...
Problem 3-36A
Agassi Company uses a job order cost system in each of its three
manufacturing departments. Manufacturing overhead is applied to
jobs on the basis of direct labour cost in Department D, direct
labour hours in Department E, and machine hours in Department
K.
In establishing the predetermined overhead rates for 2016, the
following estimates were made for the year.
Department
D
E
K
Manufacturing overhead
$1,400,000
$1,250,000
$720,000
Direct labour costs
$2,000,000
$1,250,000
$450,000
Direct labour hours
100,000...
Problem 2-4A (Video) (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on Ehe basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,170,000 $1,462,500 100,000...
Problem 2-4A (Video) (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Departme Do Review - Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,170,000 $1,462,500...
RESOURCES oters 14,1. | Problem 2-4A (Video) (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. -4 (Part Level In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department -12 (Video) Submission) -6 (Video) Submission) -4A...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $1,260,000 $1,625,000 $960,000 Direct labor costs $1,800,000 $1,375,000 $495,000 Direct labor hours 110,000 125,000 44,000...
Agassi Company uses a job order cost system in each of its
three manufacturing departments. Manufacturing overhead is applied
to jobs on the basis of direct labor cost in Department D, direct
labor hours in Department E, and machine hours in Department
K.
In establishing the predetermined overhead rates for 2020, the
following estimates were made for the year.
Department
D
E
K
Manufacturing overhead
$1,080,000
$1,500,000
$1,020,000
Direct labor costs
$1,542,857
$1,250,000
$450,000
Direct labor hours
100,000
125,000
40,000...
Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...