Question

Consider the following two projects: Year 4 Discount Rate Project A Year 0 Year 1 Year 2 Year 3 Y Cash Cash Cash Cash Cash Fl
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: D

Present value (PV) of future cash flows should be calculated first.

PV = (CF year 1 / 1.15^1) + (CF year 2 / 1.15^2) + (CF year 3 / 1.15^3) + (CF year 4 / 1.15^4)

      = (30 / 1.15) + (30 / 1.3225) + (30 / 1.520875) + (30 / 1.749006)

      = 26.086 + 22.684 + 19.725 + 17.152

      = 85.647

Now NPV should be calculated as below:

NPV = PV – Initial investment

            = 85.647 – 73

            = 12.647

Hence,

Profitability index = PV / Initial investment

                            = 12.647 / 73

                              = 0.17

Add a comment
Know the answer?
Add Answer to:
Consider the following two projects: Year 4 Discount Rate Project A Year 0 Year 1 Year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following two projects: Discount Rate Project Year 0 Cash Flow -100 -73 Year 1...

    Consider the following two projects: Discount Rate Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Year 4 Cash Flow N/A 30 .15 B The payback period for project B is closest to: Select one: A.2.2 years B.2.5 years C.2.4 years D. 2.0 years

  • Сл This Question: 1 pt Consider the following two projects: Project Year 0 Year 1 Year...

    Сл This Question: 1 pt Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 ΝΙΑ - 73 30 30 30 30 Discount Rate 0.17 0.17 A B The net present value (NPV) of project A is closest to: O A. 10.2 B. 8.2 O C. 20.4 OD. 9 Click to select your answer. Type here to search o

  • Consider the following two projects: Discount Rate Year 4 Year 3 Year 2 Year 1 Year...

    Consider the following two projects: Discount Rate Year 4 Year 3 Year 2 Year 1 Year 0 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 - 73 Project 0.16 N/A 60 50 40 0.16 30 30 30 30 The net present value (NPV) of project B is closest to: O A. 12 O B. 13.7 O. 10.9 O D. 27.4

  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.16 0.16 The net present value (NPV) of project A is closest to: O A. 11.1 B. 25.2 O C. 10.1 OD. 12.6

  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount C/F C/F C/F C/F C/F C/F C/F C/F Rate Alpha - 79 20 25 30 35 40 NA NA 15% Beta - 80 25 25 25 25 25 25 25 16% Assume that projects Alpha and Beta are mutually exclusive. The correct investment decision and the best rationale for that decision is to O A invest in...

  • Use the table for the question(s) below. Consider the following two projects: Year 4 Project Year...

    Use the table for the question(s) below. Consider the following two projects: Year 4 Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Cash Flow N/A 30 Discount Rate 15 15 A The internal rate of return (IRR) for project A is closest to: Select one: A. 21.6% B. 23.3% C. 42.9%

  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.1 0.1 The net present value (NPV) of project A is closest to: A. 28.5 B. 56.9 C. 25 D. 22.8

  • Consider the following two projects: 763,088.5469 Proiect Year 0 Year 1 Year 2 Year 3 Year...

    Consider the following two projects: 763,088.5469 Proiect Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 N/A - 7330 30 Discount Rate 0.14 0.14 30 The net present value (NPV) of project A is closest to: O A 17.6 O B. 15.5 O C. 14.1 OD 35.1 What is the internal rate of return (IRR) of an investment that requires an initial investment of...

  • You are asked to evaluate the following two projects for the Norton corporation. Use a discount...

    You are asked to evaluate the following two projects for the Norton corporation. Use a discount rate of 10 percent. Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods. Project X (Videotapes of the Weather Report) ($ 24,000 Investment) Year Cash Flow $12,000 10,000 11,000 10,600 Project Y (Slow-Motion Replays of Commercials) ($44,000 Investment) Year Cash Flow $ 22,000 15,000 16,000 18,000 w a. Calculate the profitability index for project...

  • You are asked to evaluate the following two projects for the Norton corporation. Use a discount...

    You are asked to evaluate the following two projects for the Norton corporation. Use a discount rate of 12 percent. Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods. Project X (Videotapes of the Weather Report) ($36,000 Investment) Year Cash Flow $18,000 16,000 17,000 16,600 Project Y (Slow-Motion Replays of Commercials) ($56,000 Investment) Year Cash Flow $ 28,000 21,000 22,000 24,000 Hemt a. Calculate the profitability index for project X....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT