Answer: | |||
Calculation of NPV | |||
Formula will will use here | |||
NPV = | Present value of Cash inflows - Initial cost | ||
Initial cost = | 100.00 | ||
Year | Cash Inflows | Present value factor @ 17% | Present value of cash inflows |
1 | 40.00 | 0.85470 | 34.19 |
2 | 50.00 | 0.73051 | 36.53 |
3 | 60.00 | 0.62437 | 37.46 |
4 | 0.00 | 0.53365 | 0.00 |
Total | 108.18 | ||
NPV | |||
Present vallue of cash inflows | 108.18 | ||
Less: Initial cost | 100.00 | ||
NPV | 8.18 | ||
So, the NPV of project A is closest to $8.20 (Answer) |
Сл This Question: 1 pt Consider the following two projects: Project Year 0 Year 1 Year...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.16 0.16 The net present value (NPV) of project A is closest to: O A. 11.1 B. 25.2 O C. 10.1 OD. 12.6
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.1 0.1 The net present value (NPV) of project A is closest to: A. 28.5 B. 56.9 C. 25 D. 22.8
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount C/F C/F C/F C/F C/F C/F C/F C/F Rate Alpha - 79 20 25 30 35 40 NA NA 15% Beta - 80 25 25 25 25 25 25 25 16% Assume that projects Alpha and Beta are mutually exclusive. The correct investment decision and the best rationale for that decision is to O A invest in...
Consider the following two projects: Year 4 Discount Rate Project A Year 0 Year 1 Year 2 Year 3 Y Cash Cash Cash Cash Cash Flow Flow Flow Flow Flow -100405060 N/A -73 30 30 30 30 The profitability index for project B is closest to: O Select one: A. 12.64 B. 23.34 C.0.12 D. 0.17
Consider the following two projects: Discount Rate Year 4 Year 3 Year 2 Year 1 Year 0 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 - 73 Project 0.16 N/A 60 50 40 0.16 30 30 30 30 The net present value (NPV) of project B is closest to: O A. 12 O B. 13.7 O. 10.9 O D. 27.4
Consider the following two projects: 763,088.5469 Proiect Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 N/A - 7330 30 Discount Rate 0.14 0.14 30 The net present value (NPV) of project A is closest to: O A 17.6 O B. 15.5 O C. 14.1 OD 35.1 What is the internal rate of return (IRR) of an investment that requires an initial investment of...
Consider the following two projects: Discount Rate Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Year 4 Cash Flow N/A 30 .15 B The payback period for project B is closest to: Select one: A.2.2 years B.2.5 years C.2.4 years D. 2.0 years
This Question: 1 pt Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/F C/F CIF CIF C/F CIF CIF CIF Rate Alpha - 79 20 25 35 40 NA NA 12% Beta 80 25 25 25 25 25 25 13% 30 25 The net present value (NPV) for project beta is closest to: O A. $31 O B. $37 O C. $24 D. $21
Use the table for the question(s) below. Consider the following two projects: Year 4 Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Cash Flow N/A 30 Discount Rate 15 15 A The internal rate of return (IRR) for project A is closest to: Select one: A. 21.6% B. 23.3% C. 42.9%
Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Project C/F C/F C/F C/F C/F C/F C/F C/F Alpha - 79 20 25 30 35 40 NA N/A Beta -80 25 25 25 25 25 25 25 Discount Rate 14% 15% The net present value (NPV) for project beta is closest to: