Dear student, only one question is allowed at a time. I am answering the first question
Present value factor
= 1 / ( 1 + Rate of interest) ^ Number of years
So, PV Factor for year 2 will be
= 1 / ( 1.14 ^ 2)
= 1 / 1.2996
= 0.769468
The following table shows the calculations :
Calculations | Years | 0 | 1 | 2 | 3 | 4 |
A | Cash Flow | -100 | 40 | 50 | 60 | 0 |
B | PV Factor | 1 | 0.877193 | 0.769468 | 0.674972 | 0.59208 |
C = A x B | Present Value | -100.00 | 35.09 | 38.47 | 40.50 | 0.00 |
D = Sum C | Net Present Value | 14.06 |
So, the Net Present Value of Project A is closest to $14.1 and so option C is the correct option
Consider the following two projects: 763,088.5469 Proiect Year 0 Year 1 Year 2 Year 3 Year...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount C/F C/F C/F C/F C/F C/F C/F C/F Rate Alpha - 79 20 25 30 35 40 NA NA 15% Beta - 80 25 25 25 25 25 25 25 16% Assume that projects Alpha and Beta are mutually exclusive. The correct investment decision and the best rationale for that decision is to O A invest in...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.16 0.16 The net present value (NPV) of project A is closest to: O A. 11.1 B. 25.2 O C. 10.1 OD. 12.6
Сл This Question: 1 pt Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 ΝΙΑ - 73 30 30 30 30 Discount Rate 0.17 0.17 A B The net present value (NPV) of project A is closest to: O A. 10.2 B. 8.2 O C. 20.4 OD. 9 Click to select your answer. Type here to search o
Consider the following two projects: Discount Rate Year 4 Year 3 Year 2 Year 1 Year 0 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 - 73 Project 0.16 N/A 60 50 40 0.16 30 30 30 30 The net present value (NPV) of project B is closest to: O A. 12 O B. 13.7 O. 10.9 O D. 27.4
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.1 0.1 The net present value (NPV) of project A is closest to: A. 28.5 B. 56.9 C. 25 D. 22.8
Use the table for the question(s) below. Consider the following two projects: Year 4 Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Cash Flow N/A 30 Discount Rate 15 15 A The internal rate of return (IRR) for project A is closest to: Select one: A. 21.6% B. 23.3% C. 42.9%
Consider the following two projects: Year Cash Flow (Beta) Cash Flow (Zeta) 0 −$25,000 −$28,000 1 12,000 14,000 2 10,000 13,000 3 9,000 11,000 Instructions: 1. Using company cost of capital 15%, calculate the following investment criteria for both projects: a. Payback period b. Net Present Value (NPV) c. Internal Rate of Return (IRR) d. Profitability Index (PI) 2. If projects Beta and Zeta are independent, which one(s) will you choose? Why? 3. If projects Beta...
Consider the following two projects: Year 4 Discount Rate Project A Year 0 Year 1 Year 2 Year 3 Y Cash Cash Cash Cash Cash Flow Flow Flow Flow Flow -100405060 N/A -73 30 30 30 30 The profitability index for project B is closest to: O Select one: A. 12.64 B. 23.34 C.0.12 D. 0.17
Consider the following two projects: Discount Rate Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Year 4 Cash Flow N/A 30 .15 B The payback period for project B is closest to: Select one: A.2.2 years B.2.5 years C.2.4 years D. 2.0 years
This Question: 1 pt Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/F C/F CIF CIF C/F CIF CIF CIF Rate Alpha - 79 20 25 35 40 NA NA 12% Beta 80 25 25 25 25 25 25 13% 30 25 The net present value (NPV) for project beta is closest to: O A. $31 O B. $37 O C. $24 D. $21