Question

Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Project C/F C/F C/F C/F C/F C/F

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV =PV of Inflows -Initial Outflow

For Project Beta the discount rate is gven as 15%

The NPV can be computed using the excel function=NPV()

The formula used =NPV(15%,B3:B9)+B2 We get the NPV as 24.01

BS Book1 - Excel (Product Activation Failed) o X File Home Insert Page Layout Formulas Data Review View Developer Tell me wha

Add a comment
Know the answer?
Add Answer to:
Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount C/F C/F C/F C/F C/F C/F C/F C/F Rate Alpha - 79 20 25 30 35 40 NA NA 15% Beta - 80 25 25 25 25 25 25 25 16% Assume that projects Alpha and Beta are mutually exclusive. The correct investment decision and the best rationale for that decision is to O A invest in...

  • This Question: 1 pt Consider the following two projects: Year 0 Year 1 Year 2 Year...

    This Question: 1 pt Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/F C/F CIF CIF C/F CIF CIF CIF Rate Alpha - 79 20 25 35 40 NA NA 12% Beta 80 25 25 25 25 25 25 13% 30 25 The net present value (NPV) for project beta is closest to: O A. $31 O B. $37 O C. $24 D. $21

  • Consider the following two projects: Year 0 Yearl Year 2 Year 3 Year 4 Year 5...

    Consider the following two projects: Year 0 Yearl Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/E C/F C/E C/E C/F C/E C/F C/F Rate Alpha -79 20 25 30 35 40 N/A N/A 15% Beta -80 25 25 25 25 25 25 25 16% Which of the following statements is correct? Select one: A. You should invest in project Alpha since IRRAlpha > IRRBeta. B. You should invest in project Beta since NPVBeta...

  • Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year...

    Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Discount Project C/F C/F C/F C/F C/F C/F Rate Alpha -30 20 25 30 35 4 0 15% Bet =80255 255 25 16 a) Which project would you choose based on the NPV rule? b) Draw a graph showing the IRR, if IRR for project Alpha is 20% and IRR for project Beta is 22%. ਜਾ ਰ ਰ ਰ .

  • I need the solution step by step for this question please, Consider the following two projects...

    I need the solution step by step for this question please, Consider the following two projects and choose the correct answer: Year 0 Year1 Year2 Year3 Year4 Year5 Year6 Year7 Discount Rate project C/F C/F C/F C/F C/F C/F C/F C/F    Alpha - 79 20 25 30 35 40 N/A N/A 15% Beta - 80 25 25    25 25 25 25 25 16% The internal rate of return (IRR) for project Alpha is closest to: () 24.5% ()...

  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.1 0.1 The net present value (NPV) of project A is closest to: A. 28.5 B. 56.9 C. 25 D. 22.8

  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.16 0.16 The net present value (NPV) of project A is closest to: O A. 11.1 B. 25.2 O C. 10.1 OD. 12.6

  • Consider the following two projects: Discount Rate Year 4 Year 3 Year 2 Year 1 Year...

    Consider the following two projects: Discount Rate Year 4 Year 3 Year 2 Year 1 Year 0 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 - 73 Project 0.16 N/A 60 50 40 0.16 30 30 30 30 The net present value (NPV) of project B is closest to: O A. 12 O B. 13.7 O. 10.9 O D. 27.4

  • Consider the following two projects: 763,088.5469 Proiect Year 0 Year 1 Year 2 Year 3 Year...

    Consider the following two projects: 763,088.5469 Proiect Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 N/A - 7330 30 Discount Rate 0.14 0.14 30 The net present value (NPV) of project A is closest to: O A 17.6 O B. 15.5 O C. 14.1 OD 35.1 What is the internal rate of return (IRR) of an investment that requires an initial investment of...

  • Сл This Question: 1 pt Consider the following two projects: Project Year 0 Year 1 Year...

    Сл This Question: 1 pt Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 ΝΙΑ - 73 30 30 30 30 Discount Rate 0.17 0.17 A B The net present value (NPV) of project A is closest to: O A. 10.2 B. 8.2 O C. 20.4 OD. 9 Click to select your answer. Type here to search o

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT