Question

You are analyzing a project which has a $20,000 sunk cost. The project’s cost is $150,000...

You are analyzing a project which has a $20,000 sunk cost. The project’s cost is $150,000 and the expected cash flows are: (Use this info for questions #1-4)

            Year 1: $60,000

            Year 2: $0

            Year 3: $100,000

            Year 4: $0

            Year 5: $60,000

The discount rate is 18% (the required return is also 18%). The required payback is 2.3 years.

1. Calculate the internal rate of return (must have correct set-up and your answer should be between two consecutive whole percentages). Accept or reject?

2. Calculate the discounted payback period. Accept or reject?

3. Calculate the payback period. Accept or reject?

4. Calculate the NPV.  Accept or reject?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) IRR is the rate at which NPV is 0,Let us assume rate to be 14%

Statement showing NPV at 14%

Year Cash flow PVIF @ 14% Present value
1 60000 0.8772 52632
2 0 0.7695 0
3 100000 0.6750 67497
4 0 0.5921 0
5 60000 0.5194 31162
Total 151291
Less: Initial Investment 150000
NPV 1291

Now let us assume rate to be 15%,

Statement showing Npv at 15%

Year Cash flow PVIF @ 15% Present value
1 60000 0.8696 52174
2 0 0.7561 0
3 100000 0.6575 65752
4 0 0.5718 0
5 60000 0.4972 29831
Total 147756
Less: Initial Investment 150000
NPV -2244

Using interpolation one can find IRR

Rate NPV
14% 1291
15% -2244
1% up -3535
? -1291

=1291/3535 = 0.36

Thus IRR = 14+0.36

=14.36%

Since IRR is less than NPV, project should be rejected

2) Statement showing discounted cash payback period

Year Cash flow PVIF @ 18% Present value Cummulative Present value
1 60000 0.8475 50847.46              50,847.46
2 0 0.7182 0.00              50,847.46
3 100000 0.6086 60863.09            111,710.54
4 0 0.5158 0.00            111,710.54
5 60000 0.4371 26226.55            137,937.10

Total cummulative present value at end of year 5 is 137,937.1$ which is less that projects initial cost i.e 150,000$

hence project won't pay back even at end of year 5

one should reject the project

3) Statement showing payback period

Year Cash flow CummulatiCash flow
1 60000 60000
2 0 60000
3 100000 160000
4 0 160000
5 60000 220000

Using interpolation one can find payback period

Year Cummulative cash flow
2 60000
3 160000
1 up 100000
? 90000

=1*90000/1000000

=0.9

Thus payback period = 2 + 0.9 =2.9 years

Reject the project

4) Statement showing NPV

Year Cash flow PVIF @ 18% Present value
1 60000 0.8475 50847
2 0 0.7182 0
3 100000 0.6086 60863
4 0 0.5158 0
5 60000 0.4371 26227
Total 137937
Less: Initial Investment 150000
NPV -12063

Since NPV is negative , project should be rejected

Add a comment
Know the answer?
Add Answer to:
You are analyzing a project which has a $20,000 sunk cost. The project’s cost is $150,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Provide your solutions in sequential order below the line. Round final answer to the nearest hundredth....

    Provide your solutions in sequential order below the line. Round final answer to the nearest hundredth. Show all work and circle your final answer. You are analyzing a project which has a $20,000 sunk cost. The project's cost is $150,000 and the expected cash flows are: (Use this info for questions #1-4) Year 1: $60,000 Year 2: $0 Year 3: $100,000 Year 4: $0 Year 5: $60,000 The discount rate is 18% (the required return is also 18%). The required...

  • Allegheny Steel Corp. is considering a 9-year project with an initial cost of $38,000 and total...

    Allegheny Steel Corp. is considering a 9-year project with an initial cost of $38,000 and total Project Cash Flows of $9,400 each year of the project. The required return is 15% and discounted payback needs to be 5 years or less. Reject based on discounted payback Accept based on discounted payback Payback cannot be calculated Accept based on NPV Reject based on NPV

  • You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200...

    You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200 I$87,300 $41,000 I$39,000 1 12 4 Required payback period 2.5 years Required return 8.50% the project. Based on the profitability index of 0.97; accept for this project, you should 1.05; accept 1.18; accept 0.97; reject 1.05; reject Question 15 You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200 $87,300 $41,000 $39,000 Required payback period 2.5 years Required...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...

  • JR inc. would like your help in analyzing a new venture. The lead manager thinks that the project will create a net cash...

    JR inc. would like your help in analyzing a new venture. The lead manager thinks that the project will create a net cash inflow of $100,000 next year and this net cash flow will grow at 4%/year indefinitely. The initial cost of the project will be $1,000,000 and the required rate of return is ten percent. Calculate NPV, the PI, and the Discounted Payback Period.

  • You are considering a project that will require an initial outlay of $200,000. This project has...

    You are considering a project that will require an initial outlay of $200,000. This project has an expected life of four years and will generate after-tax cash flows to the company as a whole of $60,000 at the end of each year over its five-year life. Thus, the free cash flows associated with this project look like this: Year Free Cash Flow 0 -150,000 1 60,000 2 60,000 3 60,000 4 60,000 Given a required rate of return of 10%...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR Cash Flow.....($200).....$850.......($700).......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Reject the project because the NPV is less than zero b. Accept the project because the IRR is greater than zero c. Accept the project because the NPV is greater than zero d. Accept the project because the payback...

  • A project will cost $95,000 today and there will be an additional cost in year 3...

    A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000.  The project will have the following projected cash flows:             Yr                                Cash Flow             1                                  $30,000             2                                  $50,000             3                                  $0             4                                  $50,000 The discount rate is 14%.  Calculate the modified internal rate of return.  Do you accept or reject?  (Must have correct set-up and your answer should be between two consecutive whole percentages.)

  • 3. If a project costs $150,000 and is expected to return $40,000 annually, what is the...

    3. If a project costs $150,000 and is expected to return $40,000 annually, what is the conventional payback period (PBP)? What is the discounted payback period (DPBP) at 18%7 (20 points) Conventional payback period - (please include the calculating process) Discounted payback period: (Fill in the following table for DPBP and specify your answer) Ending cash Period (n) Cash flow Cost of fund balance 0 -150,000 -150,000 40,000 40,000 40,000 40,000 40,000 40,000

  • What information does the payback period provide? Suppose you are evaluating a project with the expected...

    What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $300,000 Year 2 $425,000 Year 3 $450,000 Year 4 $500,000 If the project’s weighted average cost of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT